Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium Scrum PSPO-I Dumps Questions Answers

Page: 1 / 13
Total 173 questions

Professional Scrum Product Owner (PSPO I) Exam Questions and Answers

Question 1

What is the timebox for the Sprint Planning event?

(choose the best answer)

Options:

A.

Monthly.

B.

Whenever it is done.

C.

8 hours for a one-month Sprint.

D.

4 hours for a one-month Sprint.

Buy Now
Question 2

Your management has asked you to take the lead in the development of a new product. Six teams new to Scrum will build this product.

You have gathered a number of requirements and ideas into an early form of a Product Backlog. How would you minimize dependencies between the Scrum Teams?

(choose the best answer)

Options:

A.

You create an independent Product Backlog per Scrum Team.

B.

You divide Product Backlog items among the six Product Owners.

C.

You identify the dependencies and re-order the Product Backlog for the other fiveProduct Owners.

D.

You work with the Developers on how to best analyze and break apart the work.

E.

You raise this as an impediment with the Scrum Master.

Question 3

Which of the following are the Developers accountable for?

(choose the best two answers)

Options:

A.

Organizing the work required to meet the Sprint Goal.

B.

Selecting the Product Owner.

C.

Reporting productivity.

D.

Creating a plan for the Sprint, the Sprint Backlog.

Question 4

Which of the following are appropriate topics for discussion during a Sprint Retrospective?

(choose the best two answers)

Options:

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Question 5

Who should make sure everyone on the Scrum Team does their tasks for the Sprint?

(choose the best answer)

Options:

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Scrum Team.

E.

All of the above.

Question 6

A Scrum Master is working with a Scrum Team that has Developers in different physical

locations. The Developers meet in a variety of meeting rooms and have much to do logistically

(for example: reserve meeting rooms and set up conference calls) before the Daily Scrum.

What action should the Scrum Master take?

(choose the best answer)

Options:

A.

Allow the Developers to self-manage and determine for themselves what to do.

B.

Ask the Developers to alternate who is responsible for meeting setup.

C.

Set up the meeting and tell the Scrum Team that is how it will be done.

D.

Inform management and ask them to solve it.

Question 7

Which of the following is required by Scrum?

(choose the best answer)

Options:

A.

Sprint Retrospective.

B.

Developers must stand up at the Daily Scrum.

C.

Sprint Burndown Chart.

D.

Release Planning.

E.

All of the above.

Question 8

What should the Scrum Team do during the first Sprint?

(Choose the best answer)

Options:

A.

Make up a plan for the rest of the project.

B.

Define the major product features and a release plan architecture.

C.

Create at least one valuable and useful Increment.

D.

Analyze, describe, and document the requirements for the subsequent Sprints.

Question 9

True or False: A Product Owner with multiple teams working on one product should maintain separate Product Backlogs for each team.

Options:

A.

True

B.

False

Question 10

Who determines how many Product Backlog items the Developers select for a Sprint?

(choose the best answer)

Options:

A.

The Scrum Team

B.

The Developers.

C.

The Product Owner.

D.

The Scrum Master.

E.

The stakeholders attending Sprint Planning.

Question 11

Who creates the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Master

B.

The Scrum Team

C.

The Product Owner

D.

The Developers

Question 12

A Product Backlog is:

(choose the best three answers)

Options:

A.

An exhaustive list of upfront approved requirements to be implemented.

B.

Managed by the Product Owner.

C.

An inventory of things to be done for the Product.

D.

Ordered based on priority, value, dependencies, and risk.

E.

Only visible to the Product Owner and stakeholders.

Question 13

What activities would a Product Owner typically undertake in the period between the end of the

current Sprint and the start of the next Sprint?

(choose the best answer)

Options:

A.

There are no such activities. The next Sprint starts immediately after the currentSprint.

B.

Refine the Product Backlog.

C.

Update the project plan with stakeholders.

D.

Work with the Quality Assurance departments on the Increment of the current Sprint.

Question 14

When can Developers cancel a Sprint?

(choose the best answer)

Options:

A.

When functional expectations are not well understood.

B.

When the selected Product Backlog items for the Sprint become unachievable.

C.

They cannot. Only Product Owners can cancel Sprints.

D.

When the Product Owner is absent too often.

E.

When a technical dependency cannot be resolved.

Question 15

How much of the Sprint Backlog must be defined during the Sprint Planning event?

(choose the best answer)

Options:

A.

Just enough to understand design and architectural implications.

B.

Enough so the Developers can create their forecast of what work they can do.

C.

The entire Sprint Backlog must be identified and estimated by the end of Sprint Planning.

D.

Just enough tasks for the Scrum Master to be confident in the Developers ' understanding of the Sprint.

Question 16

Who is accountable for managing the progress of work during a Sprint?

(choose the best answer)

Options:

A.

The Developers.

B.

The most junior member of the team.

C.

The Scrum Master.

D.

The Product Owner.

Question 17

True or False: Multiple Scrum Teams working on the same product or system all select work

from the same Product Backlog.

Options:

A.

True

B.

False

Question 18

Five new Scrum Teams have been created to build one product. A few of the Developers on one of the Scrum Teams ask the Scrum Master how to coordinate their work with the other teams. What should the Scrum Master do?

(choose the best answer)

Options:

A.

Teach them that it is their responsibility to work with the other teams to create anintegrated Increment that is inclusive of all five team ' s work.

B.

Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.

C.

Visit the five teams each day to inspect that their Sprint Backlogs are aligned.

D.

Teach the Product Owner to work with the lead developers on ordering ProductBacklog in a way to avoid too much overlap during a Sprint.

Question 19

What might indicate to a Product Owner that she needs to work more with the Scrum Team?

(choose the best answer)

Options:

A.

The acceptance criteria do not appear to be complete.

B.

She is not working full time with the Scrum team.

C.

People leave the Scrum Team.

D.

The Increment presented at the Sprint Review does not reflect what she thought she had asked for.

Question 20

True or False: Product Owners must specify complete acceptance criteria for a Product

Backlog item before the Developers can select the item in Sprint Planning.

Options:

A.

True

B.

False

Question 21

Which three of the following are true about Scrum?

(choose the best three answers)

Options:

A.

Scrum implements self-management by replacing Project Managers with ScrumMasters.

B.

Scrum is based on empiricism and lean thinking.

C.

Scrum is a framework for developing and sustaining complex products.

D.

Scrum is a methodology where you can pick and choose which parts of Scrumyou think will work for your environment.

E.

Each component of Scrum serves a specific purpose and is essential to Scrum ' ssuccess and your usage of Scrum to develop complex products.

Question 22

During a Sprint Retrospective, the Developers propose moving the Daily Scrum to only occur

on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum

Master to recommend?

(choose the best two answers)

Options:

A.

Have the Developers vote.

B.

Acknowledge and support the self-managing team ' s decision.

C.

Coach the team on why the Daily Scrum is important as an opportunity to updatethe plan.

D.

Consider the request and decide on which days the Daily Scrum should occur.

E.

Learn why the Developers want this and work with them to improve the outcomeof the Daily Scrum.

Question 23

The Product Owner is the person who will be held accountable if a product does not achieve its

goals or deliver value. Does this mean that the Product Owner has final say over the Definition

of Done?

(choose the best answer)

Options:

A.

Yes, the Product Owner decides the Definition of Done. The Developers may beconsulted.

B.

No, the Scrum Team decides the Definition of Done, if it is not a standard of theorganization. The Product Owner is just one member of the Scrum Team.

Question 24

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

(choose the best answer)

Options:

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Developers ability to deliver.

D.

The Definition of Done.

E.

All of the above.

Question 25

Who has the final decision about the order of items in the Product Backlog?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The Stakeholders.

C.

The Scrum Team.

D.

The Developers.

E.

The Product Owner.

Question 26

A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses?

(choose the best two answers)

Options:

A.

Promote transparency by sharing the Product Backlog and ensuring the ProjectManager has access.

B.

Have a discussion with the Project Manager; share the current impediments andforecast for the Sprint.

C.

Show the Earned Value Analysis (EVA) report.

D.

Scrum does not have Project Managers so disregard their concerns.

E.

Share the last stakeholder briefing document prepared by the Product Owner.

Question 27

True or False: The value delivered by a product can only be determined by revenue.

Options:

A.

True

B.

False

Question 28

When is the Sprint Backlog created?

(choose the best answer)

Options:

A.

Prior to Sprint Planning.

B.

During refinement.

C.

During the Sprint Retrospective.

D.

During Sprint Planning.

Question 29

The Scrum Team should have all the skills needed to:

(choose the best answer)

Options:

A.

Complete the project within the date and cost as calculated by the Product Owner.

B.

Do all of the development work, except for specialized testing that requires additionaltools and environments.

C.

Turn Product Backlog items into a valuable, useful Increment.

Question 30

Which statement best describes the Sprint Backlog as the output of the Sprint Planning?

(choose the best answer)

Options:

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Developers plan for the Sprint.

E.

It is ordered by the Product Owner.

Question 31

What are two effective ways for a Scrum Team to ensure security concerns are satisfied? (choose the best two answers)

Options:

A.

Add security concerns to the Definition of Done.

B.

Delegate the work to the security department.

C.

Have the Scrum Team create Product Backlog items for each concern.

D.

Add a Sprint to specifically resolve all security concerns.

E.

Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.

Question 32

If Product Backlog refinement is needed, when is the ideal time for refinement to take place and

who should participate?

(choose the best two answers)

Options:

A.

The Scrum Team during the current Sprint, if they have been unable duringpreceding Sprints to define Product Backlog items with enough precision tobegin work.

B.

Business analysts in the organization should do this work for the Scrum Team 1- 2 Sprints ahead of the development Sprints.

C.

The Product Owner must do this as essential work in Sprint O.

D.

The Product Owner takes the time between the end of one Sprint and the startof the next Sprint to complete refinement.

E.

The Scrum Team on an ongoing basis, defining Product Backlog items intosmaller more precise items that are ready for selection.

Question 33

How much time must a Product Owner spend with the Developers?

(choose the best answer)

Options:

A.

Enough so that the Product Owner is confident the Increment will meet the intended value.

B.

40%, or more if the stakeholders agree.

C.

As much time as the Developers tell the Product Owner to be present.

D.

100%

Question 34

Who is accountable for clearly expressing Product Backlog items?

(Choose the best answer)

Options:

A.

The Product Owner.

B.

The business analyst who represents the Product Owner.

C.

The Scrum Master.

D.

The Scrum Master, or the Scrum Master may have the Developers do it.

Question 35

Who is accountable for creating a valuable and usable Increment each Sprint?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The CEO.

C.

The Developers.

D.

The Scrum Team.

E.

The Product Owner.

Question 36

A Scrum Team has been working on a product for 9 Sprints. A new Product Owner who is new to Scrum joins the team and understands she is accountable for the Product Backlog. However, she is unsure about the purpose of the Product Backlog. She has read that the Product Backlog

should be a list of all user features for the product. She goes to the Scrum Master asking where to put the other types of requirements that are going to be taken into account. Are all of the following types of requirements acceptable on a Product Backlog?

• Stability requirements

• Performance requirements

• Product Functionality

• Documentation

• Fixes

(choose the best answer)

Options:

A.

Yes, they all belong on the Product Backlog. The Product Backlog is supposed to be the " single source of truth " for all the work for the product.

B.

No. Product Backlog is a tool for the Product Owner. The Product Owner represents the users and stakeholders. Other types of requirements should be managedseparately by the Developers. They are not the Product Owner ' s concern.

Question 37

Which approach is best for Scrum Teams in order to produce valuable Increments?

(choose the best answer)

Options:

A.

Each Developer works on the component where they feel that they can contribute.

B.

Each Scrum Team works on an independent set of components.

C.

Each Scrum Team is accountable for developing functionality from beginning to end.

D.

Each Scrum Member works only as an independent layer of the system.

Question 38

A new Developer is having continuing conflicts with existing members of the Scrum Team,

which is impacting the delivery of the Increment. If necessary, who is responsible for removing

the Developer from the Scrum Team?

(choose the best answer)

Options:

A.

The Product Owner is responsible, they control the return on investment (ROI).

B.

The Scrum Team is responsible.

C.

The Scrum Master is responsible, they remove impediments.

D.

The hiring manager is responsible, they hired the Developer.

Question 39

The Daily Scrum is an event that happens every day. What would be three key concerns if the

frequency were to be lowered to every two or three days?

(choose the best three answers)

Options:

A.

The Sprint Backlog may become inaccurate.

B.

Too much work is spent updating the Scrum board before the meeting.

C.

The Scrum Master loses the ability to update the Gantt chart properly.

D.

The Product Owner cannot accurately report progress to the stakeholders.

E.

Opportunities to inspect and adapt the Sprint Backlog are lost.

F.

Impediments are raised and resolved more slowly.

Question 40

Why does the Product Owner want the Developers to adhere to its Definition of Done?

(choose the best answer)

Options:

A.

To predict the team ' s productivity over time.

B.

To have complete transparency into what has been done at the end of each Sprint.

C.

To know what the team will deliver over the next three Sprints.

D.

To be able to reprimand the team when they do not meet their velocity goal for the Sprint.

Question 41

Who owns the Sprint Backlog?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The Scrum Team.

C.

The Product Owner.

D.

The Developers.

Question 42

What are the two responsibilities of testers in a Scrum Team?

(choose the best two answers)

Options:

A.

Tracking quality metrics.

B.

Scrum has no " tester " role.

C.

Verifying the work of programmers.

D.

The Developers are responsible for quality.

E.

Finding bugs.

Question 43

What may be included in the Sprint Backlog?

(choose the best answer)

Options:

A.

User Stories.

B.

Tasks.

C.

Use Cases.

D.

Tests.

E.

Any of the above (or others) which are a decomposition of the selected ProductBacklog items.

Question 44

Why is it important that there is only one Product Owner per product?

(choose the best three answers)

Options:

A.

The Scrum Master knows who acts as their backup while on vacation.

B.

It would confuse the stakeholders if they had to work with more than one person.

C.

It is clear who is accountable for the ultimate value of the product.

D.

It helps avoid barriers to effective communication and rapid decision-making.

E.

The Scrum Team always knows who determines the order of the ProductBacklog.

Question 45

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

(choose the best answer)

Options:

A.

The Project Manager.

B.

The Scrum Team.

C.

The Developers.

D.

The Product Owner.

Question 46

The job of a Product Owner focuses on the following:

(choose the best two answers)

Options:

A.

Working with customers and stakeholders to identify the most valuable productrequirements.

B.

Writing clear, transparent User Stories.

C.

Being with the Scrum Team all the time, just in case they need me to clarify arequirement.

D.

Clearly communicating project or release status and strategies to customers andstakeholders.

Question 47

Which of the following are true about the length of the Sprint?

(choose the best answer)

Options:

A.

The length of the Sprint should be proportional to the work that is done in betweenSprints.

B.

All Sprints must be one month or less.

C.

Sprint length is determined during Sprint Planning, and should hold the time it willtake to build the planned features in the upcoming Sprint, but does not include timefor any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough tomake sure the Scrum Team can deliver what is to be accomplished in the upcomingSprint

Question 48

True or False: Scrum has a role called " Project Manager " .

Options:

A.

True

B.

False

Question 49

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the best answer)

Options:

A.

The Product Owner.

B.

The Quality Assurance Team.

C.

The Scrum Team.

D.

The Developers.

E.

The Scrum Master.

Question 50

Why is the Daily Scrum held at the same time and same place?

(choose the best answer)

Options:

A.

The Product Owner demands it.

B.

Rooms are hard to book and must be booked in advance.

C.

The place can be named.

D.

The consistency reduces complexity.

Page: 1 / 13
Total 173 questions