Question 33

How much time must a Product Owner spend with the Developers?

(choose the best answer)

Options:

A.

Enough so that the Product Owner is confident the Increment will meet the intended value.

B.

40%, or more if the stakeholders agree.

C.

As much time as the Developers tell the Product Owner to be present.

D.

100%

Question 34

Who is accountable for clearly expressing Product Backlog items?

(Choose the best answer)

Options:

A.

The Product Owner.

B.

The business analyst who represents the Product Owner.

C.

The Scrum Master.

D.

The Scrum Master, or the Scrum Master may have the Developers do it.

Question 35

Who is accountable for creating a valuable and usable Increment each Sprint?

(choose the best answer)

Options:

A.

The Scrum Master.

B.

The CEO.

C.

The Developers.

D.

The Scrum Team.

E.

The Product Owner.

Question 36

A Scrum Team has been working on a product for 9 Sprints. A new Product Owner who is new to Scrum joins the team and understands she is accountable for the Product Backlog. However, she is unsure about the purpose of the Product Backlog. She has read that the Product Backlog

should be a list of all user features for the product. She goes to the Scrum Master asking where to put the other types of requirements that are going to be taken into account. Are all of the following types of requirements acceptable on a Product Backlog?

• Stability requirements

• Performance requirements

• Product Functionality

• Documentation

• Fixes

(choose the best answer)

Options:

A.

Yes, they all belong on the Product Backlog. The Product Backlog is supposed to be the " single source of truth " for all the work for the product.

B.

No. Product Backlog is a tool for the Product Owner. The Product Owner represents the users and stakeholders. Other types of requirements should be managedseparately by the Developers. They are not the Product Owner ' s concern.