SAFe Release Train Engineer (RTE 6.0) Questions and Answers

Question 29

At the end of day two of the Program Increment (PI) Planning event, the team's final plan review covers what information?

Options:

A.

Team Features, Stories, and team-level enablers

B.

Changes to capacity and load, final PI objectives, program risks and impediments

C.

Changes to iteration goals, measured velocity, and dependencies

D.

Planned Features, uncommitted objectives, and ROAMed risks

Question 30

During which part of an Inspect and Adapt event would differences between planned business value and actual business value be presented?

Options:

A.

Retrospective

B.

Problem-solving workshop

C.

Quantitative and qualitative measurement

D.

PI system demo

Question 31

What action can result in reduced collaboration between teams during the Program Increment (PI) Planning event?

Options:

A.

Skip the Inspect and Adapt event

B.

Include inexperienced team members

C.

Start the Agile Release Train without a System Team in place

D.

Overprepare for PI Planning

Question 32

Why would a Release Train Engineer use an Iteration and Program Increment Calendar?

Options:

A.

To know the cycle time between important team and train events

B.

To ensure that key ceremonies don't conflict with non-SAFe ceremonies

C.

To create a BVIR of the important team and ART milestones

D.

To visualize the Agile Release Train's cadence and synchronization