SAFe Release Train Engineer (RTE 6.0) Questions and Answers

Question 65

Program Increment (PI) Planning is a major event that requires preparation, coordina-tion, and communication. What are two key areas a Release Train Engineer should focus on to support a successful PI Planning event? (Choose two.)

Options:

A.

Organizational readiness - Strategic alignment; roles, teams, and train setup

B.

Architectural readiness - Defining the Architectural Runway

C.

Operational readiness - Facilitating PI events such as scrum of scrums, Iteration Planning, and System emo

D.

Facilities readiness - Space and logistics for the event

E.

Process readiness - The operational rhythm that enables SAFe governance

Question 66

What is the recommended duration of an Iteration in SAFe?

Options:

A.

Three weeks

B.

Two weeks

C.

Four weeks

D.

Six weeks

Question 67

What is the most accurate definition of DevOps?

Options:

A.

A set of tools and processes that govern how code is deployed

B.

A process that provides visibility to impediments between writing code and deliv-ering value

C.

A mindset, culture, and set of technical practices that emphasizes close coopera-tion to provide value to the Customer

D.

A method that ensures Operations works with Development every day to deliver value