Question 41

Communicating a project's design and technical specifications to the client and stakeholders is part of the ___________of the project.

Options:

A.

scope of work

B.

needs analysis

C.

close out procedure

D.

bidding phase

Question 42

An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter

Options:

A.

8

B.

16

C.

32

D.

64

Question 43

Alter a company's senior executive management meeting the CEO issues a mandate to automate a new-client on-boarding process that would effectively eliminate the current manual paper-based process. The assigned program sponsor selects a program manager

Both the program sponsor and the program manager must ensure that the program charier contains which of the following?

Options:

A.

Justification, benefits management plan, scope, and resources needed

B.

Justification, benefits strategy scope and resource management plan

C.

Justification, outcomes, scope, and stakeholder considerations

D.

Justification, benefits management plan, program business case and stakeholder considerations