Question 29

The program manager wants to increase the team's commitment to the program objectives. The program manager should do which of the following?

Options:

A.

Work with the sponsor lo identify the organization's best practices

B.

Work with the program stakeholders and program management office to identify the organization's best practices

C.

Work with the program management office to identify the organization's best practices

D.

Work with the sponsor, program stakeholders, and the program management office to identify the organization's best practices

Question 30

A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk

What should the program manager do to monitor and control the supplier?

Options:

A.

Use expert judgment and update the program procurement plan

B.

Seek stakeholder approval of program procurement management activities

C.

Examine performance reports, audits, and inspections

D.

Review proposal evaluation criteria, risk analyses, and mitigation strategies

Question 31

An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)

Options:

A.

0.006 m2 (8 in2)

B.

0.008 m2 (12 in2)

C.

0.040 m2 (60 in3)

D.

0.60 m2 (80 in3)

Question 32

The type of apparatus housed in TRs varies greatly in size, purpose and function. Which two of the following active equipment is included? (Select two options.)

Options:

A.

Cross-connect facilities

B.

Telecommunication’s equipment

C.

Environmental controls

D.

Lighting controls

E.

Building system equipment