Question 13

To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.

What should the program manager do?

Options:

A.

Document the concerns that program goals may be affected and present at the next program governance board review meeting for guidance and actions to be taken.

B.

Advise the program sponsor that the program will continue and follow the program management plan, unless the change control board (CCB) has approved changes to the plan

C.

Work with the project managers of the affected components to implement fast tracking and update the resource management plan accordingly

D.

Evaluate critical success factors and key performance indicators (KPIs) to monitor benefits throughout the program's life cycle

Question 14

A program manager is working on benefits. The program team created and updated a benefits register earlier in the program. The benefits register should include which of the following?

Options:

A.

List of planned benefits, earned value (EV) and responsible person

B.

List of planned benefits, measurement method, and component mapping

C.

List of planned benefits, benefit creator and realization date

D.

List of planned benefits, stakeholders, and risk level

Question 15

In an office area, a consultant needs to add the location of a fax machine to the plan. What is the approximated floor area that a fax machine occupies?

Options:

A.

0.2 sq m (2 sq ft)

B.

0.5 sq m (5 sq ft)

C.

1 sq m (10 sq ft)

D.

1.5 sq m (16 sq ft)

E.

2 sq m (20 sq ft)

Question 16

XYZ Company hires you to make its transitioning procedure more effective in meeting close-out requirements. You review XYZ's transitioning procedures to eliminate any that do not belong in the close-out phase.

Which of the following procedures should you removed?

Options:

A.

Managing the transition from the "As-ls" state to the "To-Be" or Target Stale

B.

Reviewing the status of benefits with the stakeholders and program sponsor

C.

Managing any required transition to operations

D.

Documenting lessons learned in the organizational database