Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI PMI-002 Based on Real Exam Environment

Page: 19 / 28
Total 748 questions

Certified Associate in Project Management (CAPM) Certification Questions and Answers

Question 73

Activity Resource Requirements is an input to ____________ :

Options:

A.

Estimate Activity Durations

B.

Control Schedule

C.

Sequence Activities

D.

Estimate Activity Resources

Question 74

All are output of verify scope.

Options:

A.

Precedence diagramming method (PDM)

B.

Arrow diagramming method (ADM)

C.

Expert judgment

D.

Network templates

Question 75

A Reserve Analysis technique is NOT used during __________.

Options:

A.

Control Costs

B.

Estimating Activity Duration

C.

Determine Budget

D.

Estimate Costs

Question 76

Which of the following is an output of a Verify Scope process?

Options:

A.

Formal acceptance

B.

WBStemplate

C.

SOW acceptance

D.

Rework

Page: 19 / 28
Total 748 questions