Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Free PMI-002 PMI Updates

Page: 21 / 28
Total 748 questions

Certified Associate in Project Management (CAPM) Certification Questions and Answers

Question 81

___________ coordinates people and other resources to carry out the plan.

Options:

A.

Work Breakdown Structure

B.

Resource planning

C.

Resource leveling

D.

Executing process

Question 82

Contingency planning is a means to _____ risks to the project through a formal process and provides the resources to meet the risk events.

Options:

A.

Address

B.

Classify

C.

Assign

D.

Resolve

Question 83

An input of the Collect Requirements process is a/an:

Options:

A.

Project Charter

B.

Project schedule

C.

Strategic plan

D.

Historical information

Question 84

A Trend Analysis is best described as:

Options:

A.

Examining project performance over time

B.

Calculating Earned Value

C.

Calculating Cost Variance

D.

Analyzing performance of similar projects over time

Page: 21 / 28
Total 748 questions