Certified Associate in Project Management (CAPM) Certification Questions and Answers

Question 73

You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

Options:

A.

Schedule

B.

Assumption

C.

Constraint

D.

Planning process

Question 74

In PMBOK, the buyer is ________ to the project team.

Options:

A.

Internal

B.

External

C.

Outside

D.

Assigned

Question 75

Stakeholder influence is greatest at the ______ of the project.

Options:

A.

Beginning

B.

Closing

C.

Controlling

D.

Executing

Question 76

Which of the following must be measured regularly to identify variances from the plan.

Options:

A.

Stakeholder requirements

B.

Project performance

C.

Control Schedule

D.

Project controls