Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

CA0-001 Premium Exam Questions

Page: 3 / 20
Total 525 questions

Certified Associate in Project Management (CAPM) Certification Questions and Answers

Question 9

You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?

Options:

A.

$-00,000

B.

$200,00

C.

$50,000

D.

None of the above

Question 10

Project just went into inclusion mode. This means that project __________.

Options:

A.

Has become part of the business processes

B.

Has been accepted by the sponsor and the client

C.

Will be closed due to lack of resources

D.

None of the above

Question 11

If a project with a SPI of 1.8, what you tell?

Options:

A.

The project is running ahead of the schedule

B.

The project is running behind of the schedule

C.

Resources assigned to the project cost 1.8 units

D.

None

Question 12

Make-or-buy decisions measure the costs of both options. What are the two options?

Options:

A.

Direct ar|d Indirect

B.

Tactical and Strategic

C.

Management and Project

D.

0n|y Tactical

Page: 3 / 20
Total 525 questions