A customer requested a quote for a 64Gb Fibre Channel system between two data centers with a distance of 95 KM / 60 MI between the locations, with a requirement for 14 F-ports on each switch.
Refer to exhibit

Which statement is true about the given configuration?
You are designing a solution for a customer that will support a virtualization workload based on HPE Synergy. Your customer has the following requirements:
Dual-socket HPE Synergy compute nodes running ESXi 8.x with maximum memory supported
Each node should have access to shared storage from HPE Alletra Storage MP B10000
All virtual machines should be protected against host failure
All virtual machines with vGPU must be protected with Fault Tolerance
All compute nodes should boot from disks located in the D3940 Storage Modules protected with RAID 1
All frames should be managed as one logical enclosure to simplify management
All compute nodes should support two network ports with the maximum Ethernet connectivity speed
You are reviewing a proposal that you must verify. The proposal consists of:
3 x HPE Synergy 12000 frames
2 x HPE Synergy Composer2 modules
4 x HPE Virtual Connect SE 100Gb F32 Modules for Synergy
4 x HPE Synergy 50Gb Interconnect Link Modules
3 x HPE Synergy D3940 Storage Modules, each with 20 SSD drives
1152 core VMware vSphere Enterprise Plus subscriptions
36 x HPE Synergy 480 Gen11 compute nodes
Each SY480 Gen11 is configured with:
A single Platinum CPU with 32 cores
HPE Synergy 6820C 25/50Gb Converged Network Adapter
HPE Synergy 5830C 32Gb Fibre Channel Host Bus Adapter
HPE MR416i-o Gen11 12G SAS Mezzanine Controller
Which two statements are true regarding the proposal? (Select two.)
Your customer is planning to buy a new hardware platform for their HPC application.
They are considering an environment with 150 HPE Cray XD2000 systems with XD225v and XD220v servers.
Your customer has the following requirements for a management platform:
Supports Ubuntu Linux 24.04 operating system
Supports bare metal server operating system provisioning
Has the ability to install operating system in parallel on multiple nodes
Management platform is highly available
You are exploring HPE Performance Cluster Manager (HPCM) as a solution.
What statement is true in this scenario?