Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Fundamentals-of-Crew-Leadership Exam Dumps : Module 46101 Fundamentals of Crew Leadership

PDF
Fundamentals-of-Crew-Leadership pdf
 Real Exam Questions and Answer
 Last Update: Jun 15, 2025
 Question and Answers: 25 With Explanation
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
Fundamentals-of-Crew-Leadership exam
PDF + Testing Engine
Fundamentals-of-Crew-Leadership PDF + engine
 Both PDF & Practice Software
 Last Update: Jun 15, 2025
 Question and Answers: 25
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
Fundamentals-of-Crew-Leadership Engine
 Desktop Based Application
 Last Update: Jun 15, 2025
 Question and Answers: 25
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Module 46101 Fundamentals of Crew Leadership Questions and Answers

Question 1

Which of the following statements regarding the consequences of willful safety violations is TRUE?

Options:

A.

Only the negligent injured worker can be fined.

B.

Only upper company management can be fined.

C.

Employers cannot be held liable for an employee's injury or death.

D.

Superintendents and crew leaders can be held financially and criminally liable.

Buy Now
Question 2

What is one of the many traits effective leaders should have?

Options:

A.

the ability to communicate the goals of a project

B.

a perfectionist nature that ensures they will not make mistakes

C.

the motivation to carry the workload alone in order to achieve a goal

D.

the ability to make decisions without listening to the opinions of others

Question 3

A crew of electricians is needed to run 1,000 feet of conduit, and the estimator determined that two electricians could complete the job in an eight-hour day. What is the required productivity rate per person for the conduit install?

Options:

A.

31.25 feet per hour

B.

62.5 feet per hour

C.

130 feet per hour

D.

150 feet per hour