A company is expanding an existing vSphere deployment to meet new demands from the business. The following requirements have been identified for the expanded infrastructure:
REQ001- It must support enhanced vMotion compatibility (EVC) mode for Intel "Nehalem" Generation (Intel Xeon Core i7) processors.
REQ002- It must be accessible via an API.
REQ003- It must support a variety of operating systems.
REQ004- It must notify administrators whenever a virtual machine is connected to more than one network.
Which requirement would be classified as a technical (formerly non-functional) requirement?
An architect is designing a vSphere-based private cloud solution to support the following customer requirements:
The solution should support running 5,000 concurrent production compute workloads across the primary and secondary sites.
The solution should support running 1,000 development compute workloads within the secondary site.
The solution should support up to 50 management workloads across the primary and secondary site.
The solution must ensure the isolation of virtual infrastructure management operations between management and compute workloads.
The solution must ensure that hosting of any virtual infrastructure management workloads does not impact the amount of capacity available for compute workloads.
The solution must ensure that all production compute workloads are physically isolated from development compute workloads.
The solution must ensure that the operational management of compute workloads in the secondary site is possible in the event of a disaster affecting the primary site.
A combination of which four design decisions should the architect make to support the requirements? (Choose four.)
An architect is documenting the design for a new multi-site vSphere solution. The customer has informed the architect that the workloads hosted on the solution are managed by application teams, who must perform a number of steps to return the application to service following a failover of the workloads to the secondary site. These steps are defined as the Work Recovery Time (WRT). The customer has provided the architect with the following information about the workloads:
Critical workloads have a WRT of 12 hours
Production workloads have a WRT of 24 hours
Development workloads have a WRT of 24 hours
All workloads have an RPO of 4 hours
Critical workloads have an RTO of 1 hour
Production workloads have an RTO of 12 hours
Development workloads have an RTO of 24 hours
The customer has also confirmed that the Disaster Recovery solution will not begin the recovery of the development workloads until all critical and production workloads have been recovered at the secondary site.
What would the architect document as the maximum tolerable downtime (MTD) for each type of workload in the design?