Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

FIDIC CCM Exam With Confidence Using Practice Dumps

Exam Code:
CCM
Exam Name:
Certified Contract Manager
Certification:
Vendor:
Questions:
140
Last Updated:
Apr 11, 2026
Exam Status:
Stable
FIDIC CCM

CCM: Contract Manager Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the FIDIC CCM (Certified Contract Manager) exam? Download the most recent FIDIC CCM braindumps with answers that are 100% real. After downloading the FIDIC CCM exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the FIDIC CCM exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the FIDIC CCM exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Certified Contract Manager) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA CCM test is available at CertsTopics. Before purchasing it, you can also see the FIDIC CCM practice exam demo.

Related FIDIC Exams

Certified Contract Manager Questions and Answers

Question 1

(Which two of the following statements are correct regarding types of Claims under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The limit in time referred to in Sub-Clause 20.2.1 (also known as time bar) applies to all types of Claims.

B.

If a Claim is submitted as per sub-paragraph (c) of Sub-Clause 20.1, this is dealt with by the Engineer or Employer’s Representative (in case of FIDIC Silver Book) as per Sub-Clause 3.7/3.5.

C.

If a Claim is submitted as per sub-paragraphs (a) or (b) of Sub-Clause 20.1, it is dealt with in accordance with Sub-Clause 20.2, which specifically covers claims for time and/or money. Part of the procedure under Sub-Clause 20.2 is for a payment and/or an extension of time-related claim to be agreed or determined by the Engineer/Employer’s Representative (in case of the FIDIC Silver Book) in accordance with Sub-Clause 3.7/3.5.

D.

The time bar only applies to Contractor’s Claims and not to Employer’s Claims.

Buy Now
Question 2

(Which two answers show characteristics of Test on Completion or Test After Completion under the FIDIC Silver Book (edition 1999)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

In case of failure of the Test on Completion, the Employer may accept the Works, thereby reducing the Contract Price.

B.

The Employer can either opt for Tests on Completion or Tests after Completion, but not both.

C.

Tests after Completion are carried out by the Employer.

D.

Although Tests after Completion fail, it may be considered as passed when performance damages specified in the contract are paid by the Contractor.

Question 3

Which two statements are correct regarding the FIDIC Red Book (edition 2017)?

Options:

A.

Words and expressions stated in Sub-Clause 1.1 Definitions do not apply in respect of Specifications and Drawings.

B.

Contract Data contains information which is required by certain Sub-Clauses in the General Conditions.

C.

There is never a difference in effect whether in the Particular Conditions when the term " Works " is used, or when the term " works " is used.

D.

In some cases, if a certain information is not provided in the Contract Data, the relevant Sub-Clause shall not be applicable.