Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

FIDIC CCM Exam With Confidence Using Practice Dumps

Exam Code:
CCM
Exam Name:
Certified Contract Manager
Certification:
Vendor:
Questions:
100
Last Updated:
Feb 24, 2026
Exam Status:
Stable
FIDIC CCM

CCM: Contract Manager Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the FIDIC CCM (Certified Contract Manager) exam? Download the most recent FIDIC CCM braindumps with answers that are 100% real. After downloading the FIDIC CCM exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the FIDIC CCM exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the FIDIC CCM exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Certified Contract Manager) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA CCM test is available at CertsTopics. Before purchasing it, you can also see the FIDIC CCM practice exam demo.

Related FIDIC Exams

Certified Contract Manager Questions and Answers

Question 1

Which of the following situations form legally binding contracts? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities)

Options:

A.

The Employer received the Contractor's Letter of Tender and issued a Letter of Intent.

B.

The Employer and the Contractor signed the Contract Agreement.

C.

The Employer received the Contractor's Letter of Tender and issued a conditional Letter of Acceptance.

D.

The Employer received the Contractor's Letter of Tender and issued Letter of Acceptance.

Buy Now
Question 2

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

Options:

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.

B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.

C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.

D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.

Question 3

You are the Contract Manager of the Employer's Representative in a Thermal Power Plant Project. The Contract for this project is EPC Turnkey Contract using the FIDIC Silver Book (edition 2017) with a Contract Price of 28 million USD. The Employer's Requirements require that: "the Contractor design in accordance with international and national technical regulations, and standards, [etc.]".

For piling works, the Employer's Requirements state that the Contractor will design according to a specific national standard for piling works NTS-PW-01. After all piles for the jetty have been installed, a pile load test on lateral bearing capacity shows that actual lateral bearing capacity is much lower than the calculated lateral bearing capacity. It was later revealed by the Technical Standard Committee that there was a typo mistake during preparation of the NTS-PW-01 (translated from a foreign standard). The lateral bearing capacity of installed piles had been substantially overestimated as a result of this typo. Contractor submits a claim for 200,000 USD regarding extra costs for installing additional piles as a result of errors in the Employer's Requirements.

In the hydrological information of Site Data provided by the Employer, the annual high water level is 4.0m. However, during the design stage, with updated data from local stations along the rivers, the Contractor found out there was a mistake in the calculation. The annual high water level should be 4.5m. As a result, the Contractor has to design and build additional flood walls along the river to protect the Plant from flooding. The Contractor claims an amount of 300,000 USD to construct the flood wall, based on Unforeseeable difficulties.

As the Employer's Representative, after you have consulted with both Parties but failed to reach agreement, you will make a fair determination of the Claims of the Contractor.

In your "Notice of the Employer's Representative's determination", what is your determination for the Contractor?

Options:

A.

The Contractor is not entitled to either of the Claims.

B.

The Contractor is entitled to the Claim for additional costs in relation to the piling, based on errors in the Employer's Requirement only.

C.

The Contractor is entitled to the Claim for the additional flood wall based on Unforeseeable difficulties only.

D.

The Contractor is entitled to both Claims.