Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

AACE International PSP Exam With Confidence Using Practice Dumps

Exam Code:
PSP
Exam Name:
Planning & Scheduling Professional (PSP) Exam
Certification:
Questions:
163
Last Updated:
Jul 3, 2025
Exam Status:
Stable
AACE International PSP

PSP: Professional Level Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the AACE International PSP (Planning & Scheduling Professional (PSP) Exam) exam? Download the most recent AACE International PSP braindumps with answers that are 100% real. After downloading the AACE International PSP exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the AACE International PSP exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the AACE International PSP exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Planning & Scheduling Professional (PSP) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA PSP test is available at CertsTopics. Before purchasing it, you can also see the AACE International PSP practice exam demo.

Related AACE International Exams

Planning & Scheduling Professional (PSP) Exam Questions and Answers

Question 1

You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

Options:

A.

Not suitable for complicated projects with multiple planned critical paths.

B.

Accuracy is increased by inserting delaying events into the as-planned schedule.

C.

Not suitable for projects with long durations.

D.

Less accurate as the analysis advances through the project.

Buy Now
Question 2

Which is NOT an industry-recognized methodology for quantifying critical delay?

Options:

A.

Gantt Chart.

B.

Periodic Windows.

C.

Collapsed As-Built.

D.

Time Impact.

Question 3

Resource planning must take all of the following into account except for:

Options:

A.

Types of materials, equipment and labor skills required to complete the project.

B.

Earned value techniques established for the project.

C.

Time available to complete the project.

D.

Cash flow (expenditure) limitations for completing work on the project.