Question 21

Refer to the exhibit by clicking on the EXHIBIT button above.

If the glulam beam and CLT panels all require a fire-resistance rating of 2 hours, what is the required fire-resistance rating in hours for the structural connections between the glulam and CLT?

Options:

A.

0, since they are hidden fasteners

B.

1

C.

2

D.

3, to provide an additional safety factor

Question 22

In mass timber construction of Type IV-C, the fire-resistance ratings of bearing walls are permitted to be reduced by _____ where supporting a roof only.

Options:

A.

30-minutes

B.

45-minutes

C.

1-hour

D.

2-hours

Question 23

In Type IV-C construction, the fire-resistance rating provided by protection over a connection can be determined by which of the following?

Options:

A.

Testing the fasteners used in the assembly.

B.

Testing the protection covering the connection.

C.

Calculating the temperature rise of the structural element being protected.

D.

Calculating the temperature rise of the supported member used in the connection.

Question 24

Refer to the exhibit by clicking on the EXHIBIT button above.

In the detail shown, what is the required tolerance in inches between the steel beam web and CLT?

Options:

A.

3/16

B.

1/2

C.

2

D.

3