Question 21

Of the various types of data shown which is NOT representative of Variable Data.

Options:

A.

Child’s height is 4 foot 3 inches

B.

Three employees wore hard hats

C.

Car burned 2.7 gallons of gasoline

D.

Train was going 140 kilometers per hour

Question 22

Measurement __________ is defined as the difference between the observed and the expected values for a given set of data.

Options:

A.

Breadth

B.

Linearity

C.

Range

D.

Bias

Question 23

The Waste of Overproduction is defined as ______________________.

Options:

A.

The unnecessary movement of people and equipment

B.

The liability of materials that are bought, invested in and not immediately sold or used

C.

Producing more than the next step needs or more than the customer buys

D.

The extra movement of material

Question 24

An operator checks that all boxes being packed contain enough products to fill the box. However, each box getting filled has a different number of products in it. This is a Reproducibility problem, not a Repeatability problem.