Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

IASSC ICBB Based on Real Exam Environment

Page: 10 / 11
Total 300 questions

IASSC Lean Six Sigma – Black Belt Questions and Answers

Question 37

What conclusion is most correct about the Experimental Design shown here with the response in the far right column?

Options:

A.

No factor has enough statistical confidence greater than 95% to have an impact on the response rate

B.

Constant, Adv and Bev are the only factors statistically affecting the response rate with 95% confidence or more

C.

If the Adv is increased from the low level to the high level, the response rate increases

D.

The response level is statistically concluded to only need the Adv and Bev factors set at the low level to get the largest response rate

E.

This design does not have enough experimental runs to conclude anything as evidenced by the lack of P-values in the MINITABTM output

Question 38

Which of these graphs demonstrates conditions which would be sufficient to enable OCAP for the process? 

Options:

A.

Xbar Chart

B.

Time Series Chart

C.

Neither

D.

Both

Question 39

When we compare short-term and long-term Capability which of these is true?

Options:

A.

Cp is better for the short term

B.

Both short-term and long-term performance are alike

C.

Performance tends to improve over time

D.

Cp is better for the long-term

Question 40

A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt’s effort requiring that the average cost of an internal critical raw material component be less than or equal to $4,200 in order to stay within budget. Using a sample of 35 first article components, a Mean of the new product upgrade price of $4,060, and a Standard Deviation of $98 was estimated. Select the answer that best states the Practical Problem.

Options:

A.

If the average cost per component is $4,200 or less, then the purchase manager will introduce the new product upgrade with new components.

B.

If the average cost per component is greater than $4,200, then the purchase manager will introduce the new product upgrade with new components.

C.

Only if the average cost per product upgrade is $4,060, will the purchase manager introduce new product upgrades with new components.

D.

If the average cost per new product upgrade is less than $180, then the purchase manager will introduce the new product upgrade with new components.

Page: 10 / 11
Total 300 questions