Adobe Workfront Project Manager Certified Professional Questions and Answers

Question 21

Executive stakeholders require both current metric reports and a weekly recap on a project.

How can both needs be met?

Options:

A.

Create a program-specific dashboard for the metrics and set up a weekly automated report to send.

B.

Create a program-specific dashboard for the metrics, then download a dashboard weekly to email to the stakeholder team.

C.

Create a program-specific dashboard for the metrics and add a calendar reminder for the team to review the report.

Question 22

A project manager has been asked by their manager to create a report on the assignments everyone on the team has been given.

Which report type should they use?

Options:

A.

Task

B.

Work Item

C.

Issue

Question 23

What occurs when an individual enters a new commit date that is after the original planned date of a task?

Options:

A.

The assignee of any task that has the original task set as a predecessor is notified.

B.

The Project Owner is notified whether this change will impact the Project Timeline.

C.

The Planned Completion Date of the task automatically changes to match the new Commit Date.

Question 24

Which Workfront collection of users allows a task or issue to be assigned to multiple people?

Options:

A.

Team

B.

Group

C.

Project Team

Page: 6 / 7