PMI Professional in Business Analysis (PMI-PBA) Questions and Answers

Question 17

One of the main purposes for creating a requirements traceability matrix is to:

Options:

A.

track how requirements can be connected to the solution.

B.

provide test cases to validate solution deliverables.

C.

document stakeholder approval of project requirements.

D.

track the project solution scope.

Question 18

The stakeholders for a newly approved project are subject matter experts who are very knowledgeable in the client's business and will provide the project requirements. The project team scheduled separate sessions with each subject matter expert to identify and prioritize the requirements.

Which technique is being used?

Options:

A.

Delphi technique

B.

Brainstorming

C.

Idea and mind mapping

D.

Workshop sessions

Question 19

Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?

Options:

A.

Deliver the existing product and then begin work on the requested changes.

B.

Trace the requirements and measure the impact of the requested changes on the existing delivery date.

C.

Schedule a review by the change control board (CCB) to determine next steps.

D.

Ask the developers to implement the changes.

Question 20

A document is being created that will detail the customer's needs for a product and will include a functional model, a data model, and a glossary of terms. This document is called a:

Options:

A.

standard operating manual.

B.

business case.

C.

project charter.

D.

requirements specification.