Question 9

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

Options:

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Question 10

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

Options:

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Question 11

Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.

What should the business analyst recommend to the project manager?

Options:

A.

Ask the developer's team manager for more resources.

B.

Review the business case to reconsider the project.

C.

Hire external subject matter experts for the core project team.

D.

Ask the sponsor for more resources.

Question 12

The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:

Options:

A.

vote on the product's highest-value business needs.

B.

negotiate to best meet each department's objectives.

C.

collaborate on a product scope that aligns with the company’s objectives.

D.

delegate the decision to be made by the product sponsor.