Question 21

According to ANSI C57.12, the tank pressure under rated conditions of sealed transformers shall not exceed what value?

Options:

A.

One atmosphere

B.

Two atmospheres

C.

Three atmospheres

D.

Four atmospheres

Question 22

According to API 541, when shall the vendor provide calculated data from the final witness testing?

Options:

A.

Two weeks following testing

B.

Upon request

C.

At time of final shipment

D.

Immediately upon completion of testing

Question 23

According to IEEE C57.12.00, a durable, metal, name plate shall be affixed to each transformer by the:

Options:

A.

manufacturer.

B.

owner.

C.

purchaser.

D.

QA/QC Inspector.

Question 24

What is the purpose of an equipment risk assessment in the source inspection process?

Options:

A.

To identify the level of risk associated with failure of the supplier/vendor’s quality system

B.

To identify the level of effort for source inspection activities during the manufacture/fabrication phase of a project at the supplier/vendor facility

C.

To identify which shops will be able to bid on certain types of equipment i.e. to identify the shops that can supply equipment critical to project success

D.

To determine the level of business insurance required in the event the supplier/vendor is unable to deliver the product on time while meeting contractual agreements