Huawei H12-425_V2.0 Questions Answers

HCIP-Data Center Facility Deployment V2.0 Questions and Answers

Question 5

Which of the following requires a cooling tower or drycooler?

Options:

A.

Direct ventilation air conditioning system.

B.

DX air cooled air conditioner.

C.

CW air cooled air conditioner.

D.

DX water cooled air conditioner.

Question 6

In the water-side free cooling solution, cold water cannot be transported directly from the cooling tower to chilled conditioner?

Options:

A.

True

B.

False

Question 7

When the UPS5000-E works in normal mode, in which condition will the UPS automatically transfer to bypass mode?

Options:

A.

Mains outage occurs.

B.

The power module is overloaded for a period longer than the specified time.

C.

Power module overtemperature occurs.

D.

Bypass module hardware is faulty.

Question 8

What is the input/output voltage range of the SmartLi BCU?

Options:

A.

280415 V

B.

300400 V

C.

300480 V

D.

W00-544 V