Exact Extract — Entry Management: Equipment and Materials Acceptance (PDF page 267, training slide 22)
The package is not intact. Communicate with the EPC/customer and owner about whether to further check and receive goods.
Do not install damaged devices or connect them to the network. Onsite rectification must be approved by the customer or owner and confirmed by the R & D department.
Technical Deep Dive:
Equipment acceptance involves verifying packaging integrity, delivery documentation, product specifications, quantities, and the physical condition of equipment.
The statement is false because assessment and acceptance decisions are not exclusively assigned to the SQA and supervision engineer.
When outer packaging is damaged, the project team must communicate with the EPC, customer, and owner to determine whether further inspection and acceptance should proceed.
The SQA identifies quality risks and verifies compliance with the acceptance procedure. The supervision engineer coordinates the relevant technical inspections and construction-related activities.
However, project stakeholders must participate in decisions concerning acceptance when shipping damage or packaging nonconformities are discovered.
If the investigation reveals damage to the equipment itself, the issue must be escalated according to the applicable replacement or repair procedure.
A damaged product must not be installed, energized, or connected to the operational network merely because it appears functional.
The key distinction is between identifying the damage, assessing its technical consequences, and authorizing acceptance or corrective action. These activities may involve different responsible parties.
Final verification: B. The word only makes the statement incorrect.