Which of the following statements is TRUE'?
Which of the following statements best describes the difference between product risk and project risk in software testing?
The following diagram displays the logical dependencies between requirements and the individual requirement priorities. For example, "R2->R3" means that R3 is dependent on R2. Priority is indicated by the number next to the letter ”P" i.e. P1 has a higher priority than P2.
Which one of the following options best describes the test execution sequence using both requirement dependency and priority
Software was found lo take much more time than the stated requirement of less than one second to save a file. Upon investigation it was found that there was an unnecessary check inside a loop which was slowing down the file-save operation. The software not being able to meet the desired response time is an example of