ISTQB Certified Tester Foundation Level (CTFL v4.0) Questions and Answers

Question 89

Which of the following statements is TRUE'?

Options:

A.

Unlike functional testing, non-fundional testing can only be applied to conventional systems, not artificial intelligence-based system.

B.

Functional testing focuses on what the system is supposed to do, while white-box testing focuses on how well the system does what it is supposed to do

C.

Functional testing can be applied to all test levels, while non-functional testing can be applied only to system and acceptance test levels.

D.

Black-box test techniques and experience-based test techniques may be applicable to both functional testing and non-functional testing

Question 90

Which of the following statements best describes the difference between product risk and project risk in software testing?

Options:

A.

Product risk refers to the risk associated with the project's schedule, budget, and resources, while project risk refers to the risk associated with the quality and functionality of the software product.

B.

Product risk refers to the risk associated with issues such as delays in work product deliveries, inaccurate estimates, while project risk refers to the risk associated with the project's schedule, budget, and resources.

C.

Product risk and project risk are essentially the same and can be used interchangeably.

D.

Product risk refers to the risk associated with delays in elements such as work product deliveries and inaccurate estimates, while project risk refers to the risk associated with issues such as user dissatisfaction.

Question 91

The following diagram displays the logical dependencies between requirements and the individual requirement priorities. For example, "R2->R3" means that R3 is dependent on R2. Priority is indicated by the number next to the letter ”P" i.e. P1 has a higher priority than P2.

Which one of the following options best describes the test execution sequence using both requirement dependency and priority

Options:

A.

R2. R1, R3. R4. R5, R6. R7, R8.

B.

R1, R2, R3, R4, R5, R6, R7, R8.

C.

R2, R4. R8, R5, R1, R6, R3, R7.

D.

. R2, R1,R3,R7,R6,R5,R4,R8.

Question 92

Software was found lo take much more time than the stated requirement of less than one second to save a file. Upon investigation it was found that there was an unnecessary check inside a loop which was slowing down the file-save operation. The software not being able to meet the desired response time is an example of

Options:

A.

It is not a defect

B.

Defect

C.

Error

D.

Failure