A new retail pharmacy is designing a healthy entryway to achieve Pollution Infiltration Management. The entryway, which is 10 ft. (3 m) long and the width of the entrance, consists of a grating system and rollout mats to effectively reduce the transmission of pollutants. The entryway is vacuumed once a week by the facilities team. How should this healthy entryway be changed to meet the requirements of the standards?
At a local university, lecturers teaching in an auditorium receive feedback that students experience an echo during class.
The following is some basic information about the auditorium:
. There are a total of 200 fully upholstered seats (10 rows of 20 seats each)
. A fabric covered ceiling is installed, suspended 5 ft. (1.52 m) from the concrete slab above
. 50% of the floor is carpeted, with the other 50% bare concrete finish
. The walls are left as bare concrete
Which of the following design interventions would be most likely to reduce reverberation times in the auditorium?