Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

INTE Exam Dumps : Supply Management Integration

PDF
INTE pdf
 Real Exam Questions and Answer
 Last Update: Feb 8, 2026
 Question and Answers: 167 With Explanation
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
INTE exam
PDF + Testing Engine
INTE PDF + engine
 Both PDF & Practice Software
 Last Update: Feb 8, 2026
 Question and Answers: 167
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
INTE Engine
 Desktop Based Application
 Last Update: Feb 8, 2026
 Question and Answers: 167
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Supply Management Integration Questions and Answers

Question 1

A firm has created the following process flow diagrams depicting two possible strategies for the production of a new product line. The triangles represent inventory, and the rectangles represent processing. Each of the two options start with the same raw materials, and both create the product through two stages of processing.

Which of the following statements is correct?

Options:

A.

Option B's customers are likely to wait longer before receiving the product.

B.

Option A's product will be equally as expensive to make as Option B's.

C.

Option A's product is customizable for customers.

D.

Option B's product is an example of delayed differentiation.

Buy Now
Question 2

DEF, Inc. is in the ramp-up phase of a unique medical device. The device has a two-year life expectancy. The sales forecast for the ramp-up period is as follows:

MonthJulAugSepOctNovDecJanFeb

Unit Sales1001502006001,4002,2004,00010,000

Demand after February is expected to remain at 10,000 units per month for several months, then decrease gradually. The units are small, and thus maintaining an inventory of up to 10,000 units is possible.

There are only three suppliers capable of providing the specialized component critical to this product. The production capacities of these suppliers are as follows:

•Supplier X has a capacity of 500 units per month at a cost of S20 per unit, representing 80% of its total business

•Supplier Y has a capacity of 2,000 units per month at a cost of S2O.5O per unit, representing 50% of its total business

•Supplier Z has a capacity of 20,000 units per month at a cost of $20.70 per unit, representing 10% of its total business

Two of these companies—Supplier X and Supplier Y—are minority businesses.

Given this situation, DEF should contract with

Options:

A.

Supplier Z only, as it can best fulfill the forecasted demand

B.

all three companies in a tiered system, with up to 40% from Supplier X and Y's total monthly business, and the remainder going to Supplier Z

C.

Suppliers X and Y, and work with them to increase their production capability

D.

all three companies in a tiered system, with up to 5,000 units from Supplier X, 20,000 units from Supplier Y, and the remainder from Supplier Z

Question 3

A manufacturing firm redesigns its premier product to benefit from material standardization. The change will entail re-tooling costs. The firm conducts a cost benefit analysis on four possible options. Option 1 is to make no change at all. Options 2, 3, and 4 represent different re-tooling configurations involving different materials:

Option 1Option 2Option 3Option 4

Re-tooling Costs (Year 1)$0$800,000$1,000,000$1,200,000

Material Costs

Year 151,000,000$700,000$650,000$600,000

Year 2$1,100,000$750,000$700,000$650,000

Year 3SI,200,000$800,000$750,000$700,000

Year 451,300,000$850,000$800,000$750,000

Year 551,400,000$900,000$850,000$800,000

Total$6,000,000$4,000,000$3,750,000$3,500,000

Labor Costs

Year 1$1,000,000$700,000$650,000$600,000

Year 2$1,100,000$770,000$715,000S660,000

Year 3$1,210,000$847,000$786,500$726,000

Year 4$1,331,000$931,700$865,150$798,600

Year 5$1,464,100$1,024,870$951,665$878,460

Total$6,105,100$4,273,570$3,968,315$3,663,060

In addition to this, there will be a cost of $3.5 million in lost production during Year 1, should any of the re-tooling options (2, 3, or 4) be selected.

The firm wants to rank the options in order of financial preference, from the best option to the worst. Based on this information, how should the four options be ranked?

Options:

A.

2, 3, 1, 4

B.

4, 1, 3, 2

C.

4, 3, 2, 1

D.

1, 2, 3, 4