Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PRINCE2 Prince2-Practitioner Exam With Confidence Using Practice Dumps

Exam Code:
Prince2-Practitioner
Exam Name:
PRINCE2 7 Practitioner (7th Edition) Exam
Certification:
Vendor:
Questions:
293
Last Updated:
Jul 22, 2026
Exam Status:
Stable
PRINCE2 Prince2-Practitioner

Prince2-Practitioner: PRINCE2 Certification Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PRINCE2 Prince2-Practitioner (PRINCE2 7 Practitioner (7th Edition) Exam) exam? Download the most recent PRINCE2 Prince2-Practitioner braindumps with answers that are 100% real. After downloading the PRINCE2 Prince2-Practitioner exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PRINCE2 Prince2-Practitioner exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PRINCE2 Prince2-Practitioner exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (PRINCE2 7 Practitioner (7th Edition) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA Prince2-Practitioner test is available at CertsTopics. Before purchasing it, you can also see the PRINCE2 Prince2-Practitioner practice exam demo.

PRINCE2 7 Practitioner (7th Edition) Exam Questions and Answers

Question 1

While producing the Team Plan to deliver the agreed Work Package, it became apparent that the user representatives assigned 10 check some of the products were unsuitable.

Which 2 actions should the Team Manager take in response to this situation?

Options:

A.

Consult the Senior Supplier to assign suitable reviewers.

B.

Discuss the situation with Project Assurance and agree the changes or additions to the reviewers. Advise the Project Manager of this risk.

C.

Ensure the Quality Register is updated with details of the agreed amendments to the reviewers.

D.

Notify the Project Manager by raising an Exception Report explaining that the original reviewers are unsuitable.

Buy Now
Question 2

Project Scenario

Project Scenario

Calendar Project (Note: The companies and people within the scenario are fictional.)

There has been a reduction in fie number of orders at the MNO Manufacturing Company due in part to the increased marketing activities of its competitors. To help counter this, the company has decided to create a promotional calendar for next year for all its current and prospective customers. The end product of this project will be a prepared calendar pack, ready for printing. The design of the calendar will be similar to one sent out previously, and must reflect the company image as described in the existing corporate branding standards. Another project is currently producing a new company logo when is to be printed on each page of the promotional calendar. The prepared calendar pack will consist of:

    Design for each month - correctly showing at public holidays and new company logo

    Selected photographs- 12 professionally-produced photographs, showing different members of staff

    Selected paper and selected envelope - for printing and mailing the calendar

    Chosen label design - a competition to design a label will be held as part of this project

    List of customers - names and addresses of customers to whom the calendar will be sent.

The project is currently in initiation and will have two further stages:

Stage 2 will include tie activities to:

    Create the customer fast using information from the Accounts and Marketing departments

    Confirm compliance with the Data Protection Legislation

    Create a design for each month - this will be done by the internal creative team

    Select and appoint a professional photographer

    Gather photograph design ideas from previous project and agree photographic session schedule

    Prepare a production cost forecast

    Select paper and envelope.

Stage 3 will include the activities to:

    Produce and select tie professionally-taken photographs

    Hold the label design competition and choose the label design

    Assemble the prepared calendar pack.

A production cost forecast, based on the options and costs for the paper, envelope, printing and marketing of the calendar is to be produced in stage 2. However, the actual production and distribution of the calendars is not within the scope of the project. The product cost forecast will be reviewed by the Project Board to determine whether tie project should continue.

It is now 05 October and the prepared calendar pack must be delivered to the print company by 30 November, to enable printing and distribution of the calendar in time for Christmas. The cost of the activities to develop the specialist products and the cost of the project management activities are estimated to be £20,000. There is a project time tolerance of +1 week /-2 weeks and a project cost tolerance of +£6,000 / -£6,000. A change budget of £500 has been allocated but there is no risk budget.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement For each line identify the appropriate option, from options 1 to 6, that applies. Each option can be used once, more than once or not at all.

Options:

Question 3

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Which 2 statements should be recorded under the Expected dis-benefits heading?

Options:

A.

An investment of £2.5m is required.

B.

Staff morale will be negatively affected.

C.

The project will take two years to deliver.

D.

Staff may lose the opportunity to work in Information Technology.

E.

MFH will lose direct control over the outsourced business functions.