Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PRINCE2 Prince2-Practitioner Exam With Confidence Using Practice Dumps

Exam Code:
Prince2-Practitioner
Exam Name:
PRINCE2 Practitioner Exam
Certification:
Vendor:
Questions:
282
Last Updated:
Jul 12, 2025
Exam Status:
Stable
PRINCE2 Prince2-Practitioner

Prince2-Practitioner: PRINCE2 Certification Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PRINCE2 Prince2-Practitioner (PRINCE2 Practitioner Exam) exam? Download the most recent PRINCE2 Prince2-Practitioner braindumps with answers that are 100% real. After downloading the PRINCE2 Prince2-Practitioner exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PRINCE2 Prince2-Practitioner exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PRINCE2 Prince2-Practitioner exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (PRINCE2 Practitioner Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA Prince2-Practitioner test is available at CertsTopics. Before purchasing it, you can also see the PRINCE2 Prince2-Practitioner practice exam demo.

PRINCE2 Practitioner Exam Questions and Answers

Question 1

Additional Information

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Column 1 contains a number of risk responses identified by the Project Manager following an assessment of this risk. Column 2 contains a list of threat response types. For each risk response in Column 1, select from Column 2 the type of response it represents. Each option from Column 2 can be used once, more than once or not at all.

Drop down the right answer.

Options:

Buy Now
Question 2

Product Summary

A list of customers will be collated. This will use existing information from the Accounts department about current customers, and existing information from the Marketing department about prospective customers.

Using the tariff of mailing costs available from the Post Office, a production cost forecast will be produced to allow the CEO and the Marketing Director to decide whether to continue with the project. If they decide to continue, they will give the approval to launch the internal label design competition. Competition rules will be required to communicate details of the competition to the staff. The chosen label design will then be selected from the competition entries.

The photos for the calendar must be based on existing photo design ideas available from the Marketing department. The selected photos will be chosen from these. Monthly calendar displays will be created to show the required layout of each page.

Product Breakdown Structure (contains errors)

Extract from Stage Plan for stage 3.

(All entries are true statements but may not be shown under the correct heading or in the correct document).

Using the Product Summary and Product Breakdown Structure provided as additional Information for this question In the Scenario Booklet, answer the following question.

Column 1 is a list of some of the entries in the product breakdown structure. Determine whether each entry in Column 1 has been correctly shown in the product breakdown structure. Select from Column 2 the appropriate statement that correctly describes that entry. Each selection from Column 2 can be used once, more than once or not at all.

Options:

Question 3

Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

According to PRINCE2, which statement about the Configuration Management Strategy for the Outsourcing project is correct?

Options:

A.

Every project needs a Configuration Management Strategy, even if the organization has existing configuration management standards, because every project has different circumstances.

B.

A separate Configuration Management Strategy will be required for each of the suppliers within this project because each will have a different way of managing and storing products.

C.

A Configuration Management Strategy is unnecessary for this project because the MFH document control process is documented. It is acceptable simply to reference this in the Quality Management Strategy.