Month End Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PRINCE2 Prince2-Practitioner Exam With Confidence Using Practice Dumps

Exam Code:
Prince2-Practitioner
Exam Name:
PRINCE2 7 Practitioner (7th Edition) Exam
Certification:
Vendor:
Questions:
263
Last Updated:
Jan 31, 2026
Exam Status:
Stable
PRINCE2 Prince2-Practitioner

Prince2-Practitioner: PRINCE2 Certification Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PRINCE2 Prince2-Practitioner (PRINCE2 7 Practitioner (7th Edition) Exam) exam? Download the most recent PRINCE2 Prince2-Practitioner braindumps with answers that are 100% real. After downloading the PRINCE2 Prince2-Practitioner exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PRINCE2 Prince2-Practitioner exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PRINCE2 Prince2-Practitioner exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (PRINCE2 7 Practitioner (7th Edition) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA Prince2-Practitioner test is available at CertsTopics. Before purchasing it, you can also see the PRINCE2 Prince2-Practitioner practice exam demo.

PRINCE2 7 Practitioner (7th Edition) Exam Questions and Answers

Question 1

If Project tolerances were threatened, who needs to be notified?

Options:

A.

Project Board

B.

Project Manager

C.

Corporate or Programme Management

D.

Executive

Buy Now
Question 2

Scenario

A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

● Do nothing.

● Re-engineer selected business functions.

● Outsource selected business functions.

The feasibility study concluded that there was a case for outsourcing the MFH Information Technology

Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:

● One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.

● A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

● Use PRINCE2.

● Set up the project with 4 management stages:

Stage 1. Standard PRINCE2 initiation activities.

Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future service provider.

Stage 3. Request and evaluate proposals, select service provider and agree contract.

Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run

trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete.

MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years.

The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.

Which 2 statements should be recorded under the Expected benefits heading?

Options:

A.

The 10-year outsourcing contract, at current prices, will be worth £80m.

B.

Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.

C.

The total expected savings over 10 years, at current prices, is £20m.

D.

The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.

E.

The confirmed cost of the Outsourcing project is £2.5m, but with considerable savings over 10 years.

Question 3

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Roles and responsibilities heading?

Options:

A.

Each risk will be assigned a risk owner.

B.

Risks exceeding the agreed project risk tolerance will be reported to the Project Board.

C.

Risk tolerances are allocated to each stage by the Project Manager.

D.

Project Assurance will ensure that project risks are identified, assessed and controlled according to the agreed risk management procedure.

E.

An external consultant is to facilitate a risk identification workshop.