Winter Sale - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PRINCE2 Prince2-Practitioner Exam With Confidence Using Practice Dumps

Exam Code:
Prince2-Practitioner
Exam Name:
PRINCE2 7 Practitioner (7th Edition) Exam
Certification:
Vendor:
Questions:
263
Last Updated:
Jan 21, 2026
Exam Status:
Stable
PRINCE2 Prince2-Practitioner

Prince2-Practitioner: PRINCE2 Certification Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the PRINCE2 Prince2-Practitioner (PRINCE2 7 Practitioner (7th Edition) Exam) exam? Download the most recent PRINCE2 Prince2-Practitioner braindumps with answers that are 100% real. After downloading the PRINCE2 Prince2-Practitioner exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the PRINCE2 Prince2-Practitioner exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the PRINCE2 Prince2-Practitioner exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (PRINCE2 7 Practitioner (7th Edition) Exam) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA Prince2-Practitioner test is available at CertsTopics. Before purchasing it, you can also see the PRINCE2 Prince2-Practitioner practice exam demo.

PRINCE2 7 Practitioner (7th Edition) Exam Questions and Answers

Question 1

Scenario

A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.

The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.

The contract is to be reviewed and Portraits Ltd reminded of their agreement.

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.

Which 2 statements should be recorded under the Timing of risk management activities heading?

Options:

A.

During stage 4, the selected service provider will manage any risks to their Business Case and report these to the Project Manager on a weekly basis.

B.

The Project Board should hold monthly meetings to review project progress.

C.

When closing a project, the follow-on action recommendations should be updated with any risks relating to the realization of benefits after the outsourced services go live.

D.

Any new risks identified during product development should be reported to the Project Manager by the Team Manager when delivering the completed Work Package.

E.

When authorizing a stage, the Project Board will check that the exposure to risk is still acceptable.

Buy Now
Question 2

The Calendar project was delivered as originally planned, and Is now preparing for planned closure.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Options:

Question 3

PLANS

During the initiation stage, the project manager is creating the project plan.

Here are three activities carried out as part of PRINCE2’s recommended approach to planning.

As part of which step of the approach (A-F) should each activity be carried out?

Choose only one step for each activity. Each step can be used once, more than once, or not at all.

Options: