Total 138 questions

V6 ENOVIA V6 Program Central (V6R2012) Questions and Answers

Question 1

Edits to a Project Template affect:

Options:

A.

any current project that is in the Active state that was created from the template

B.

any future project that will be created from that template

C.

any project that is in the Create state that was created from that project

D.

all projects that were created from that template

Buy Now
Question 2

What are the 2 types of Projects that can be created?

Options:

A.

Concept and Project

B.

Discussion and Review

C.

Concept and Prototype

D.

Project and Prototype

Question 3

Looking at the below image, what is the P.A. column indicating?

Options:

A.

Project Accounting

B.

Project Assessment

C.

Project Assignment

D.

Project Accruals

Question 4

What does the Inherit Access radio button do?

Options:

A.

If set to Yes, access to individual folders must be specifically granted at the folder level

B.

If set to No, folder access propagates from parent folder

C.

If set to Yes, anyone with access to the parent folder will have the same access to the sub-folders

D.

If set to No, there is no access to sub-folders

Question 5

When creating a Route, if Approve is selected in the Action field, the task assignee must:

Options:

A.

choose an approval status only

B.

enter a comment only

C.

mark the task complete only

D.

enter a comment and choose an approval status

Question 6

What metric CANNOT be deleted from Critical to Quality (CTQ)?

Options:

A.

Goal

B.

Controlled

C.

Measured

D.

Predicted

Question 7

In a project with 2 tasks, and no dependencies, the critical path is identified in Red and is the:

Options:

A.

first task

B.

one with the longest time to finish

C.

second task

D.

one with the shortest time to finish

Question 8

When you click on the Program Name link in the search window, you will view a list of all the:

Options:

A.

Projects in that Program

B.

WBS for the Projects

C.

Project members

D.

Projects that are in the Active state

Question 9

In the image below what is “Line #1” indicating?

Options:

A.

Risk

B.

Dependency

C.

Current Time

D.

Issue

Question 10

If you select the Metrics Icon on the below dashboard, what happens?

Options:

A.

Data that has been generated will be displayed in a series of graphs

B.

A Financial line graph will be displayed that will show actual costs of the program

C.

A Bar chart will be displayed with the Actual and Estimated costs

D.

A Pie chart will be displayed indicating the Cost Ratio breakdown

Question 11

What does the red square in the following image, indicate?

Options:

A.

The task is not complete and the current date is after the task estimated finish date

B.

The task is not complete and there are less than 5 days before the project's estimated finish date

C.

The task is complete

D.

The task has not started

Question 12

To add a subtask under a parent task, on the WBS screen you would select the parent task and then click

Options:

A.

Add to Selected

B.

Add Under Selected

C.

Add Subtask Below

D.

Insert Under Selected

Question 13

Business goals are objectives that are satisfied by a:

Options:

A.

Project

B.

Program

C.

Task

D.

Route

Question 14

To view a Gantt Chart, select:

Options:

A.

Gantt Chart from the WBS page Actions menu

B.

Gantt Chart from the Project navigator tree

C.

Gantt Chart from the Properties menu

D.

Gantt Chart from the My Desk menu

Question 15

You can group Projects into Programs by:

Options:

A.

creating the Program first and then creating the Projects in that Program

B.

create the Projects first and then create the Program to add the Projects

C.

the order of creating Projects and Programs are not important

D.

you cannot add Projects to Programs

Question 16

Project ABC is created from a Template that has 2 bookmarks, you then update the template with a third bookmark, Project ABC

Options:

A.

will inherit the third bookmark automatically

B.

would not be updated and only have the 2 original bookmarks

C.

would have to be updated to receive the third bookmark from the Actions menu

D.

would automatically be promoted to the Archive state

Question 17

When viewing a Gantt Chart, the user can change the time grid settings to view it by....

Options:

A.

Year, Month, Week, Day, Hour, Minute

B.

Quarter, Month, Day, Hour, Minute

C.

Year, Quarter, Month, Day

D.

Year, Month, Week, Day, Minute

Question 18

What are the states of a Risk for the Out Of The Box application?

Options:

A.

Create, Active, Complete

B.

Create, Assign, Active, Review, Complete

C.

Create, Active, Archive

D.

Active, Inactive

Question 19

Which dependency code do you assign if the current task CANNOT finish until another task starts?

Options:

A.

Finish-To-Finish

B.

Finish-To-Start

C.

Start-To-Finish

D.

Start-To-Start

Question 20

In the members' page of a project, what members can you add to a project?

Options:

A.

Persons

B.

Roles

C.

Groups

D.

All of these