Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium Construction Specifications Institute CDT Dumps Questions Answers

Page: 1 / 9
Total 120 questions

Construction Documents Technologist Questions and Answers

Question 1

What is the primary purpose of MasterFormat®?

Options:

A.

To create a master list of Level 3 and Level 4 section titles

B.

To organize cost estimates by major project element

C.

To establish an order of information within specification sections

D.

To provide a uniform system for the organization of information in project manuals

Buy Now
Question 2

Which of the following is an example of quality assurance?

Options:

A.

Performing compaction testing

B.

Field observations

C.

Validating quantities for payment

D.

Scheduling and sequencing of the work

Question 3

To obtain progress payments, the contractor must submit an application for payment itemized in accordance with what?

Options:

A.

The construction schedule

B.

The subcontractor’s invoices

C.

The schedule of values

D.

The percentage of completion

Question 4

Under the design-bid-build project delivery, what is the next step after the procurement phase has ended to award the contract for construction?

Options:

A.

The contractor begins negotiating agreements with subcontractors.

B.

The owner forwards construction contract agreements to subcontractors.

C.

The contractor and owner issue an amendment indicating the project is in the construction phase.

D.

The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.

Question 5

The dual nature of design includes what two elements?

Options:

A.

Site and building

B.

Aesthetic and technical

C.

Programming and planning

D.

Innovation and authenticity

Question 6

There are over 3,500 different grades of steel. The amount of carbon, level of impurities, and additional elements all contribute to what grade steel is classified as in building projects. Therefore, which of the following is the method of specification writing used to limit lengthy descriptions of materials?

Options:

A.

American National Standards Institute (ANSI)

B.

Descriptive

C.

Performance

D.

Reference standard

Question 7

What governs Division 01 specifications and general requirements?

Options:

A.

Part I general

B.

Divisions 02-49

C.

The general conditions of the construction contract

D.

The construction drawings

Question 8

Within a project budget, which item falls into the category of a hard cost?

Options:

A.

Architect/engineer design fees

B.

Commissioning fees

C.

Project financing

D.

Land acquisition

Question 9

What is the procedure for guarding against defects and deficiencies before and during the execution of the work?

Options:

A.

Quality assurance

B.

Quality control

C.

Quality management

D.

Quality monitoring

Question 10

The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?

Options:

A.

Sheet index

B.

Cover sheet

C.

General notes

D.

Building code summary

Question 11

Which of the following terms describes the process of allocating resources for the continued performance of a building’s intended function?

Options:

A.

Budgeting

B.

Commissioning

C.

Facility management

D.

Project closeout

Question 12

Which of the following is a component of project design team coordination during the construction documents phase?

Options:

A.

Duplication of important information by each discipline

B.

Ensuring drawing note terminology is differentiated from specification terminology

C.

Requiring the owner to hire a third-party to write the Division 01 specifications independently

D.

Quality assurance tasks shared between design and consulting teams

Question 13

Which type of warranty is used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction?

Options:

A.

Warranty of title

B.

Implied warranty of merchantability

C.

Purchase warranty

D.

Extended warranty

Question 14

During the schematic design phase, a contingency line item in the estimate would be included to cover which of the following?

Options:

A.

Allowances

B.

Unit prices

C.

Unknown factors

D.

Alternates

Question 15

What must a specification section indicate?

Options:

A.

The building trade that will perform the installation

B.

The likely anticipated cost of the specified product

C.

The interrelationships that exist between the work of this section and the entire project

D.

How the owner will be compensated if the specified item is unavailable

Question 16

Cost classification, data organization, and specifications use which written formats?

Options:

A.

OmniClass and UniFormat

B.

UniFormat and MasterFormat

C.

OmniClass and MasterFormat

D.

SectionFormat® and MasterFormat

Question 17

During procurement activities, what is the process of notifying prospective or qualified bidders requesting proposals for a specific project or issuing an invitation to bid?

Options:

A.

Solicitation

B.

Instructions for Procurement

C.

Instructions to Bidders

D.

Request for Scope of Work

Question 18

Which document directly modifies the requirements of the general conditions?

Options:

A.

Division 01, General Requirements

B.

Supplementary Conditions

C.

Agreement

D.

Instructions to Bidders

Question 19

For a large transportation project, 53 borings were made and only one boring showed some contamination. Due to financial constraints, the owner is unable to provide additional funding to the design team for further investigation. Which of the following is the best course of action for the design team?

Options:

A.

Withhold the information from the bid package because the full extent remains unknown. Ask bidders to provide a unit cost for remediation.

B.

Provide a disclaimer on the contract documents about potential contaminants onsite and suggest the owner make the geotechnical report available to all bidders.

C.

Insist the owner undertake additional investigation to determine the full extent prior to putting the project out for bid.

D.

Proceed with design as is without any modifications since the results are statistically insignificant (i.e., well within expected deviations).

Question 20

Who is responsible for job site security?

Options:

A.

Owner

B.

Architect/engineer

C.

Contractor

D.

Construction manager

Question 21

Which of the following is a scaled view?

Options:

A.

Perspective

B.

Foundation plan

C.

Riser diagram

D.

Isometric

Question 22

When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?

Options:

A.

An addendum is issued to all the bidders

B.

The proposer of the substitution is notified in writing

C.

The architect/engineer accepts the substitution during the pre-bid meeting

D.

Specifications are revised and reissued to include the substitution

Question 23

Which term or word is appropriate to use in specification text?

Options:

A.

Any

B.

As per

C.

As required

D.

Work

Question 24

What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?

Options:

A.

Stipulated sum

B.

Unit price

C.

Cost-plus-fee

D.

Cost-plus-fee with guaranteed maximum price

Question 25

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

Options:

A.

Building code

B.

Quality control standard

C.

Reference standard

D.

Specification master

Question 26

During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?

Options:

A.

After the authorities having jurisdiction issues a permit

B.

Closeout phase

C.

Preconstruction phase

D.

Construction phase

Question 27

When developing an operation and maintenance (O&M) budget for a facility, what should form the basis for budget decisions?

Options:

A.

The architect/engineer’s projected operating costs

B.

The construction manager’s life cycle analysis

C.

The estimator’s preliminary project description

D.

The facility manager’s historical record of actual costs

Question 28

Which team member is actively involved and interested in all phases of the project?

Options:

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers

Question 29

Which is the reference document that includes guidelines and tools for the organization and presentation of design and construction drawings?

Options:

A.

AIA CAD Layer Guidelines

B.

National Institute of Building Sciences

C.

National BIM Standard – United States

D.

U.S. National CAD Standard

Question 30

Within the context of the construction industry, what does BIM stand for?

Options:

A.

Building Information Modeling

B.

Business Information Manual

C.

Building Interior Maintenance

D.

Building Inspection Manual

Question 31

The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?

Options:

A.

Cash allowance

B.

Quantity allowance

C.

Unit pricing

D.

Alternates

Question 32

What project scheduling technique involves setting the target date of building occupancy and then working backwards to establish preceding milestone dates?

Options:

A.

Methods technique

B.

Critical path method

C.

Front end loading

D.

Schedule of values

Question 33

A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?

Options:

A.

Record drawings

B.

Manufacturer's representative

C.

Project manual

D.

Record submittals

Question 34

When should a post-occupancy evaluation by the facility manager be performed?

Options:

A.

At the end of the correction period

B.

Three to six months after initial occupancy

C.

Just before the end of the warranty period

D.

One year after substantial completion

Question 35

How long after bid opening is a bidder required to honor their bid price for a project?

Options:

A.

It should be no less than the time period acknowledged on the bid form.

B.

The time period is thirty days for a private project and indefinitely for a public project.

C.

The time period should conform to requirements set by the Associated General Contractors of America.

D.

The time period as established by the contract for construction.

Question 36

Standards for sustainable facilities, products, and fundamental approaches emphasize the needs of what?

Options:

A.

Architect, supplier, and contractor

B.

Owner, stakeholders, and participants

C.

Public, private, and environmental health

D.

Owner team, contractor team, and design team

Page: 1 / 9
Total 120 questions