What is the primary purpose of MasterFormat®?
To create a master list of Level 3 and Level 4 section titles
To organize cost estimates by major project element
To establish an order of information within specification sections
To provide a uniform system for the organization of information in project manuals
CSI’s MasterFormat® is the standard for organizing work results–based information for building projects. In CDT study materials and CSI practice guides, its primary purpose is described as providing a uniform, consistent structure for organizing and retrieving information in:
Project manuals (specifications)
Related documents such as cost information, product literature, and some facility management data
MasterFormat does this by dividing the work into Divisions and Sections with standardized titles and numbers so that everyone (owner, A/E, contractor, suppliers) can find information in the same place across different projects. That is exactly what Option D states.
Why the others are incorrect:
A. Master list of Level 3 and Level 4 section titles – MasterFormat includes level 3 and level 4 titles, but listing those is a means to the end, not the primary purpose.
B. Organize cost estimates by major project element – That is closer to the stated use of UniFormat®, which organizes by systems and assemblies rather than work results.
C. Establish order of information within specification sections – That is the role of SectionFormat™ and PageFormat™, not MasterFormat.
Relevant CSI references (no links):
CSI MasterFormat® Introduction and User Guide – purpose and scope statements.
CSI Construction Specifications Practice Guide – chapter on organizing specifications with MasterFormat, SectionFormat, and PageFormat.
CSI CDT Study Materials – section on “Organizing Project Manuals.”
Which of the following is an example of quality assurance?
Performing compaction testing
Field observations
Validating quantities for payment
Scheduling and sequencing of the work
In CSI / CDT usage, quality assurance (QA) and quality control (QC) are distinct concepts:
Quality Assurance (QA) focuses on planning, processes, and preventive actions put in place before and during the work to help ensure the required quality will be achieved. It is about systems and procedures.
Quality Control (QC) focuses on inspection, testing, and verification to determine whether the constructed work conforms to the requirements of the Contract Documents.
Typical examples:
QA examples (process-oriented):
Developing and following a project-specific quality plan.
Coordinating scheduling and sequencing of the work so trades do not interfere with one another and work is done under appropriate conditions.
Prequalification of contractors, subcontractors, and testing agencies.
Establishing and enforcing submittal procedures and preinstallation meetings.
QC examples (inspection/testing):
Field testing (e.g., concrete cylinder tests, soil compaction tests).
Visual inspection of installed work.
Checking that installed products match submittals and specifications.
Looking at the options:
A. Performing compaction testing – This is a field test used to verify densities and is clearly quality control, not QA.
B. Field observations – These are performed by the A/E or others to observe and verify that work appears to be in general conformance; this is quality control.
C. Validating quantities for payment – This is a contract administration / cost control activity, not primarily a quality activity.
D. Scheduling and sequencing of the work – This is planning and coordination done in advance so the project can proceed efficiently, correctly, and without damaging completed work. Because it is a procedure-based, preventive activity, CSI places this type of planning under quality assurance.
Therefore, the example of quality assurance is “Scheduling and sequencing of the work” (Option D).
Relevant CSI / CDT References (titles only, no links):
CSI Project Delivery Practice Guide – sections on “Quality in Project Delivery” and distinctions between QA and QC.
CSI Construction Specifications Practice Guide – discussions of quality requirements, testing, and inspection.
CDT Body of Knowledge – domain on “Construction Phase: Quality Assurance and Quality Control.”
To obtain progress payments, the contractor must submit an application for payment itemized in accordance with what?
The construction schedule
The subcontractor’s invoices
The schedule of values
The percentage of completion
CSI describes the schedule of values as the breakdown of the contract sum allocated to portions of the work (often by specification section, building system, or major components). It is used as the basis for reviewing progress payments.
In CSI-aligned practice:
Before the first application for payment, the contractor submits a schedule of values to the A/E for review.
Each line item represents a portion of the work with an assigned dollar amount.
Every application for payment is itemized against that schedule—showing the percentage complete and corresponding dollar amount for each item.
Thus, the contractor’s application is organized and itemized in accordance with the schedule of values, enabling the A/E and owner to evaluate progress in a consistent, transparent way. That matches Option C.
Why the others are incomplete or incorrect in this context:
A. The construction schedule – The construction schedule shows time and sequencing, not the cost breakdown used to itemize payment requests.
B. The subcontractor’s invoices – These may support the contractor’s internal accounting but do not define how the application for payment must be structured for the owner.
D. The percentage of completion – Percentage of completion is important, but it is applied to each line item in the schedule of values. The question asks what the application must be itemized in accordance with, which is the schedule of values, not just percentages.
CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – sections on construction phase payment procedures.
CSI CDT Body of Knowledge – payment applications and use of schedule of values.
Standard conditions of the contract as discussed in CSI materials – provisions on progress payments.
Under the design-bid-build project delivery, what is the next step after the procurement phase has ended to award the contract for construction?
The contractor begins negotiating agreements with subcontractors.
The owner forwards construction contract agreements to subcontractors.
The contractor and owner issue an amendment indicating the project is in the construction phase.
The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In Design-Bid-Build (DBB), CSI describes a clear, linear sequence of phases:
Programming and design
Procurement (bidding/negotiation and selection of contractor)
Award of the construction contract
Construction
At the end of the procurement phase, the owner has received and evaluated bids, determined the successful bidder, and is ready to award the contract. CSI’s project delivery guidance explains that the award step typically involves:
Issuing a Notice of Award or letter of intent to the successful bidder; and/or
Forwarding the owner–contractor agreement (and other contract forms) for execution.
Only after this step do the parties fully execute the contract and the owner issues a Notice to Proceed, marking the official start of the construction phase. This matches Option D:
The owner issues a letter of intent or forwards the owner-contractor agreement to the successful bidder.
Why the other options are incorrect:
A. The contractor begins negotiating agreements with subcontractors.Subcontractor negotiations and subcontracts typically occur after the contractor has been formally awarded and has a binding contract with the owner. This is not the immediate step that awards the contract for construction.
B. The owner forwards construction contract agreements to subcontractors.The owner’s contract is with the prime contractor, not with subcontractors. Subcontracts are between the prime contractor and subcontractors. The owner does not award contracts directly to subs in standard DBB.
C. The contractor and owner issue an amendment indicating the project is in the construction phase.There is normally no “amendment” to enter the construction phase. The project enters the construction phase upon execution of the owner–contractor agreement and issuance of the Notice to Proceed, not by amendment.
Key CSI References (titles only):
CSI Project Delivery Practice Guide – chapters on Design-Bid-Build and the Procurement and Contract Award processes.
CSI Construction Specifications Practice Guide – discussions on contract formation and Notice of Award/Notice to Proceed.
CSI CDT Body of Knowledge – “Project Delivery Methods” and “Procurement and Award of Contract.”
The dual nature of design includes what two elements?
Site and building
Aesthetic and technical
Programming and planning
Innovation and authenticity
CSI’s project delivery and CDT materials describe design as having a dual nature:
An aesthetic (or qualitative/artistic) side – concerned with form, appearance, spatial experience, and how the built environment is perceived and used.
A technical side – concerned with structural integrity, building systems, code compliance, constructability, performance, and cost.
In the broader project-management literature you’ve uploaded, the design and construction process is described as blending technical requirements with broader qualitative and organizational goals. For example, the project life cycle discussion notes that each stage involves both technical and managerial activities, reflecting the need to satisfy functional, performance, and experiential objectives simultaneously.
CSI’s CDT framework builds on this by emphasizing that:
The architect/engineer must respond to owner values (aesthetics, image, function) and
Technical constraints and criteria (codes, standards, performance, budget, schedule).
This is what is commonly summarized in CDT study materials as the “dual nature of design” – aesthetic and technical.
Why the other options do not match CSI’s phrasing:
A. Site and building – Both are important aspects of design, but CSI’s dual-nature concept is not expressed as site vs. building.
C. Programming and planning – These are phases or processes that precede or support design, not the two “natures” of design itself.
D. Innovation and authenticity – Desirable qualities, but not the canonical CSI pair.
Thus, the correct pair that matches CSI’s description of the dual nature of design is Option B – Aesthetic and technical.
CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – “The Design Stage” (discussion of design as both artistic/aesthetic and technical/problem-solving).
CSI CDT body of knowledge – conceptual overview of the designer’s responsibilities and
There are over 3,500 different grades of steel. The amount of carbon, level of impurities, and additional elements all contribute to what grade steel is classified as in building projects. Therefore, which of the following is the method of specification writing used to limit lengthy descriptions of materials?
American National Standards Institute (ANSI)
Descriptive
Performance
Reference standard
CSI identifies four primary methods of specifying in construction specifications:
Descriptive
Performance
Reference standard
Proprietary
A reference standard specification method uses published standards from recognized organizations to define material, product, or workmanship requirements, rather than repeating long technical descriptions in the spec section.
Applied to steel:
Instead of writing long paragraphs about carbon content, alloying elements, strength, ductility, etc., the spec writer can call for a specific ASTM, AISC, or other recognized standard, such as “ASTM A992 steel shapes” or “ASTM A36 carbon steel.”
This “short” specification points to a standard that already contains the detailed technical requirements, thereby limiting lengthy descriptions in the project specification while still ensuring clear, enforceable quality requirements.
That is exactly what the question describes: using a method of specifying to avoid long, repeated descriptions for complex materials like steel with many grades. Therefore the correct answer is:
D. Reference standard
Why the other choices are incorrect:
A. American National Standards Institute (ANSI)ANSI is a standards organization, not a method of specifying. A reference standard method could incorporate ANSI standards, but the method is “reference standard,” not “ANSI.”
B. DescriptiveDescriptive specifying is the opposite of what the question is asking to avoid. It involves writing out detailed properties, materials, and installation requirements in full text, which leads to lengthy descriptions.
C. PerformancePerformance specifying focuses on required results or performance criteria (e.g., strength, deflection, fire rating), allowing the contractor or manufacturer to choose how to meet those criteria. It is not specifically aimed at avoiding long material descriptions by referencing existing published standards, which is the hallmark of reference standard specifying.
CSI-aligned references (no external links):
CSI Construction Specifications Practice Guide – chapter on Methods of Specifying (descriptive, performance, reference standard, proprietary).
CSI CDT Study materials – topics on methods of specifying and use of reference standards (ASTM, AISC, ANSI, etc.) to define material requirements.
What governs Division 01 specifications and general requirements?
Part I general
Divisions 02-49
The general conditions of the construction contract
The construction drawings
In CSI practice, Division 01 – General Requirements is written to coordinate with, expand, and supplement the Conditions of the Contract (i.e., the General and Supplementary Conditions). It does not stand on its own; it is governed by and must remain consistent with the General Conditions, which are higher in the contract document hierarchy.
The usual contract-document structure is:
Agreement
General Conditions (baseline rights, responsibilities, and procedures)
Supplementary Conditions (modify/extend general conditions)
Division 01 – General Requirements (administrative and procedural details)
Divisions 02–49 (technical specifications)
Division 01 then sets detailed project procedures “in accordance with” the Conditions of the Contract. For example, a construction management plan in your files refers to requirements being governed by a Division 01 specification (“Section 01 32 00, Project Schedule Specification Outline”), which provides project-specific procedural detail building on the contract conditions.
So:
The General Conditions establish the baseline contract obligations.
Division 01 must follow and not contradict those conditions.
Technical divisions (02–49) further detail materials and execution, again within the framework set by the Conditions of the Contract and Division 01.
Therefore, the Division 01 General Requirements are governed by the general conditions of the construction contract, making Option C correct.
CSI-aligned references (no URLs):
CSI Construction Specifications Practice Guide – chapters on “Conditions of the Contract” and “Division 01 – General Requirements.”
CSI Project Delivery Practice Guide – sections on the hierarchy of contract documents and coordination between Conditions and specifications.
Within a project budget, which item falls into the category of a hard cost?
Architect/engineer design fees
Commissioning fees
Project financing
Land acquisition
In CSI and general construction budgeting practice, project costs are often discussed in terms of:
Hard costs – also called direct construction costs, generally associated with the actual construction of the facility (labor, materials, equipment, and construction-related services).
Soft costs – professional services and non-construction expenses, such as design fees, legal fees, financing costs, some testing and inspections, and administrative costs.
Other development costs, such as land acquisition, that may be tracked separately from construction vs. soft costs.
Within that framework:
Hard costs are those closely tied to getting the building or facility physically constructed and operational. In many project budgets, commissioning work that is specified as part of the construction/contractor’s scope (functional testing of systems, demonstrating performance, etc.) is treated with the construction scope and appears with construction-related costs.
Among the four items given:
Architect/engineer design fees (A) – clearly a soft cost, part of professional services for planning and design, not part of direct construction.
Project financing (C) – interest during construction, loan fees, and similar items are typically categorized as financing/soft costs, entirely separate from construction.
Land acquisition (D) – usually tracked as a separate property or development cost, not within the construction hard-cost category.
Commissioning fees (B) – frequently included in the construction or closeout scope (and often in specifications under Division 01 or relevant technical Divisions) and directly associated with making systems function as intended. When commissioning is contracted as part of the construction contract (which is a common CSI-based approach), its cost is embedded in the hard construction costs.
In CDT-aligned budgeting discussions, when you’re forced to choose among these four, commissioning fees (Option B) are the closest to and most consistently treated as a construction-related (hard) cost, because they are often part of the contractor’s scope and necessary to complete and hand over a functioning facility.
The others—A/E fees, financing, and land—are clearly outside of direct construction and uniformly treated as soft or separate development costs in CSI-oriented project cost breakdowns.
Key CSI and industry references (titles only, no links):
CSI Project Delivery Practice Guide – sections on “Project Costs” and distinctions between construction cost and project cost.
CSI CDT Body of Knowledge – “Owner’s Costs, Construction Costs, and Cost Categories.”
Typical CSI-based Owner–Contractor contracts and Division 01 sections where commissioning requirements are placed within the construction scope.
What is the procedure for guarding against defects and deficiencies before and during the execution of the work?
Quality assurance
Quality control
Quality management
Quality monitoring
CSI distinguishes clearly between quality assurance (QA) and quality control (QC):
Quality assurance focuses on procedures, planning, and processes established before and during the work to prevent defects and deficiencies. It’s proactive and process-oriented—things like qualifications, mock-ups, preinstallation conferences, submittal review, and establishing methods.
Quality control focuses on inspection, tests, and verification of completed or in-progress work to identify defects and verify that requirements are met. It is more reactive and product-oriented.
The question asks for the procedure for guarding against defects and deficiencies before and during execution of the work, which clearly points to quality assurance—the preventive system of checks and requirements set up in advance and applied as the work proceeds.
Therefore, Option A – Quality assurance is correct.
Why the other options are not correct:
B. Quality control – QC is about testing and inspection of the finished or in-progress work to detect defects, not primarily about guarding against them through advance procedures.
C. Quality management – This is an overarching concept that can include both QA and QC but is not the specific procedural term CSI uses in the documents and Division 01 sections.
D. Quality monitoring – Not a standard CSI technical term in the same formal sense as quality assurance and quality control.
Key CSI-Oriented References (titles only, no links):
CSI Construction Specifications Practice Guide – sections on “Quality Requirements” and the distinction between QA and QC.
CSI Project Delivery Practice Guide – Design and Construction Phase quality processes.
CSI CDT Body of Knowledge – “Quality Requirements in Division 01 and Technical Sections.”
The names of the project, owner, architect/engineer and consultants, and the general project data such as a location map are normally included in which of the following?
Sheet index
Cover sheet
General notes
Building code summary
In CSI-based drawing organization, the cover sheet (sometimes called the title sheet) is the primary identification sheet of the drawing set. It typically includes:
Project name and project number
Owner’s name
Architect/engineer’s name and logo
Names of key consultants (structural, mechanical, electrical, etc.)
General project data (site address, legal description, gross area, etc.)
A location map or vicinity map
Sometimes a sheet index, code summary, and other global project information
CSI’s guidance for construction documents describes the cover sheet as the place where the project is formally identified and the major parties are listed so that anyone picking up the drawing set immediately knows what project it is, who the participants are, and where the project is located. This is exactly what the question is asking about.
Why the others are not correct in CSI’s sense:
A. Sheet index – A sheet index is usually a list of drawing sheets (by discipline and sheet number) and may be placed on the cover sheet or on a separate index sheet, but it does not normally carry the full set of project identification data, consultant names, and location map by itself.
C. General notes – General notes are used to provide global instructions or clarifications applicable to the drawings (e.g., dimensional conventions, typical construction requirements). They are not the primary location for listing the owner, A/E, consultants, or site location map.
D. Building code summary – A building code summary focuses on code-related data: occupancy classification, construction type, fire-resistance ratings, egress calculations, etc. While it may appear on the cover sheet or nearby sheets, it is not where CSI expects all of the names and general project data to be grouped.
So, per CSI’s standard organization of construction drawings and project manuals, the cover sheet is the correct answer.
Which of the following terms describes the process of allocating resources for the continued performance of a building’s intended function?
Budgeting
Commissioning
Facility management
Project closeout
From a CSI / CDT lifecycle perspective, the project does not end when construction is complete. CSI emphasizes the full facility life cycle, which includes:
Planning and design
Construction
Operation and maintenance
Eventual renovation, repurposing, or decommissioning
The phase during which a building is operated, maintained, and supported so that it continues to perform its intended function is typically referred to as facility management (or “facilities management”). CSI’s project delivery guidance characterizes facility management as including:
Allocating resources (staff, budget, utilities, maintenance contracts, equipment, etc.) to keep the facility functioning as intended
Planning and managing maintenance, repairs, replacements, and upgrades
Overseeing operations, safety, and performance of building systems
Coordinating with design and construction teams when future renovation or major maintenance projects are needed
Because the question specifically highlights “allocating resources for the continued performance of a building’s intended function”, this aligns directly with the responsibilities of facility management.
Why the other options do not fit this definition:
A. BudgetingBudgeting is the process of planning and assigning financial resources for a specific period or scope (project budgeting, department budgeting, etc.). It is a financial planning activity, not the overall ongoing process of managing and operating the facility to ensure it continues to function as intended.
B. CommissioningCommissioning is a quality-focused process performed around the end of construction and the start of operation to verify that building systems are planned, installed, tested, and capable of being operated and maintained in conformity with the design intent and owner’s project requirements. It is primarily a start-up and verification process, not the ongoing allocation of resources over the life of the facility.
D. Project closeoutProject closeout is the process of finishing all project work, completing punch lists, submitting record documents, warranties, training, and formally closing the contract. While closeout transitions the facility to the owner’s operations and facility management, it does not itself describe the ongoing management for continued performance.
In CSI’s project delivery model, once the project is closed out, the responsibility for keeping the building performing as intended shifts to facility management, making Option C the correct answer.
Which of the following is a component of project design team coordination during the construction documents phase?
Duplication of important information by each discipline
Ensuring drawing note terminology is differentiated from specification terminology
Requiring the owner to hire a third-party to write the Division 01 specifications independently
Quality assurance tasks shared between design and consulting teams
During the construction documents phase, CSI’s guidance emphasizes that coordination between the architect/engineer (A/E) and the various consulting disciplines (structural, mechanical, electrical, etc.) is essential to produce consistent, coordinated, and complete contract documents (drawings, specifications, and project manual). Part of that coordination is a shared quality assurance (QA) effort among the design team members.
In CSI’s practice guides and CDT body of knowledge, the following principles are stressed (paraphrased to respect copyright):
The prime design professional is responsible for overall coordination of the construction documents, but each consultant is responsible for the technical accuracy and coordination of their own portions.
Coordination includes review of cross-references, matching terminology, alignment of requirements between drawings and specifications, and resolving conflicts before bid/issue.
Quality assurance during this phase is not done in isolation; it is a team activity. Consultants and the lead design firm review each other’s work where it interfaces (e.g., architectural and mechanical coordination of ceilings and diffusers; structural and architectural coordination of openings, etc.).
Therefore, “Quality assurance tasks shared between design and consulting teams” (Option D) correctly describes a standard component of project design team coordination during the construction documents phase.
Why the other options are incorrect:
A. Duplication of important information by each disciplineCSI stresses “say it once, in the right place” as a fundamental principle. Information should not be unnecessarily duplicated because duplication increases the risk of conflict and inconsistency (for example, a requirement shown in both drawings and multiple spec sections but updated in only one location). Coordination aims to avoid duplication, not to promote it.
B. Ensuring drawing note terminology is differentiated from specification terminologyCSI emphasizes consistent terminology across drawings, specifications, and other documents. The same items (e.g., “gypsum board,” “reinforcing steel,” “membrane roofing”) should be described using the same terms in both drawings and specifications to reduce ambiguity. Coordination meetings often include checking that terminology is aligned, not intentionally differentiated.
C. Requiring the owner to hire a third-party to write the Division 01 specifications independentlyDivision 01 – General Requirements – is typically prepared or controlled by the lead design professional or specifier, in coordination with the owner. CSI materials do not identify it as a standard or required coordination practice for the owner to hire an independent third party to write Division 01 separately from the design team. That may occur on some projects, but it is not a defined component of team coordination in CSI’s CDT framework.
In summary, CSI-based construction documentation practice defines coordination during the construction documents phase as a shared responsibility among the architect/engineer and all consultants, including joint quality assurance reviews, consistency checks, and cross-discipline coordination. This aligns directly with Option D.
Key CSI References (no links):
CSI Project Delivery Practice Guide – chapters on Design Phase and Construction Documents coordination.
CSI Construction Specifications Practice Guide – sections on coordination between drawings and specifications and the role of Division 01.
CSI CDT Body of Knowledge – topics on roles and responsibilities of the design team and coordination of construction documents.
Which type of warranty is used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction?
Warranty of title
Implied warranty of merchantability
Purchase warranty
Extended warranty
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI’s treatment of warranties in construction distinguishes among several types, including:
Warranty of title – assures that the seller/contractor has good title to goods and that they are free of liens or claims.
Implied warranties – such as merchantability and fitness for a particular purpose, arising under applicable law for goods.
Express warranties – explicitly stated in the contract documents or manufacturer literature, which may include extended warranties.
In the construction context, CSI’s project delivery and specification guidance emphasizes that extended warranties (often called special warranties in specifications):
Survive completion and acceptance of the project.
Provide remedies to the owner for defects in materials and/or workmanship that appear after substantial completion, often beyond the standard one-year correction period.
Are commonly used for critical building components (e.g., roofing systems, waterproofing, major equipment) and may run for 5, 10, or more years.
This directly matches the question’s language: a warranty “used to provide a remedy to the owner for material defects or failures after completion and acceptance of construction.” That is precisely the purpose of an extended warranty in CSI-style contract documents and specifications, making Option D correct.
Why the other options are incorrect:
A. Warranty of titleThis deals with ownership and freedom from liens, not performance of materials or systems after completion. It does not address post-completion material defects.
B. Implied warranty of merchantabilityThis is a legal concept for goods: that they are fit for ordinary purposes. While it may apply in background law, it is not the specific contractual tool that owners rely on in construction documents to secure long-term remedies for material defects.
C. Purchase warranty“Purchase warranty” is not a standard CSI-defined category of construction warranty. Product or manufacturer warranties may be obtained at purchase, but the CSI terminology used in specifications and project delivery guidance is typically standard warranty, special warranty, or extended warranty, not “purchase warranty.”
Key CSI References (titles only):
CSI Project Delivery Practice Guide – sections on Warranties, Guarantees, and the Correction Period.
CSI Construction Specifications Practice Guide – guidance on specifying warranties (including extended warranties) in Division 01 and technical sections.
CSI CDT Body of Knowledge – “Contract Provisions: Warranties and Guarantees.”
During the schematic design phase, a contingency line item in the estimate would be included to cover which of the following?
Allowances
Unit prices
Unknown factors
Alternates
In CSI-based project cost planning, contingency is defined as an amount added to an estimate or budget to cover uncertainties and unknowns that cannot yet be clearly defined at the current level of design development.
CSI’s practice guides and CDT materials explain (paraphrased):
In early design phases, such as schematic design, the design is only partially developed. Important elements are still undecided, and system configurations may change. Because of this, the cost estimate is inherently less precise.
A contingency line item is therefore included to cover:
Incomplete design information,
Potential scope refinement,
Normal estimating uncertainties, and
Other unknown factors at that stage.
As the project moves into design development and later into the construction documents phase, the design becomes more complete and the uncertainty decreases, so contingency percentages typically decrease.
By contrast, CSI differentiates contingency from other estimating tools:
Allowances: Specific sums in the contract for known-but-not-fully-defined items (e.g., “flooring allowance of X per m²”). These are identified items with placeholder values, not general unknowns.
Unit prices: Agreed rates for measuring work (e.g., $/m³ of rock excavation) used when quantities are uncertain, but scope categories are known and clearly described in the documents.
Alternates: Defined options requested by the owner (additive or deductive) for comparison and selection—again, specifically described items, not “unknowns.”
Because the question specifically references the schematic design phase and asks what the contingency line item covers, the CSI-aligned answer is “Unknown factors” – Option C.
Why the other options are incorrect:
A. Allowances – These are separate, explicit line items in the estimate or specifications and are not what contingency is intended to cover.
B. Unit prices – These deal with agreed rates for work whose quantities may vary, not with broad early-phase uncertainty.
D. Alternates – Alternates are specifically described choices requested for comparison; they are priced individually, not absorbed into contingency.
Key CSI-aligned references (no links):
CSI Project Delivery Practice Guide – sections on cost planning and contingencies by phase.
CSI CDT Body of Knowledge – definitions and uses of contingency, allowances, unit prices, and alternates in estimating.
What must a specification section indicate?
The building trade that will perform the installation
The likely anticipated cost of the specified product
The interrelationships that exist between the work of this section and the entire project
How the owner will be compensated if the specified item is unavailable
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI defines a specification section as the document that:
Describes requirements for a specific portion of the Work (work results), and
Indicates how that portion relates and coordinates with other portions of the project.
In CSI’s Construction Specifications Practice Guide and SectionFormat guidance, a well-written specification section must:
Establish scope for that part of the work,
Define performance, products, and execution requirements, and
Address coordination and interface with other sections and with the work as a whole (for example, related sections, substrate preparation, connection to adjacent work, integration of components).
Thus, the specification section must indicate:
“The interrelationships that exist between the work of this section and the entire project” (Option C).
This is often handled in the “Related Sections,” “Summary,” or “Coordination” articles in Part 1 of the section, consistent with CSI’s SectionFormat.
Why the other options are incorrect:
A. The building trade that will perform the installationCSI is clear that specifications should not assign work to specific trades or contractors. Contracting strategy and trade assignments are the contractor’s responsibility. Specs define requirements, not which trade performs them.
B. The likely anticipated cost of the specified productSpecifications do not state prices or cost; they describe quality and performance requirements. Cost estimating is a separate function (often using UniFormat/MasterFormat structures) and is not written into the specification text.
D. How the owner will be compensated if the specified item is unavailableCompensation, changes in cost, and substitutions are handled through contract conditions and change procedures (General Conditions, Supplementary Conditions, Division 01), not within individual specification sections as a general rule.
Relevant CSI references (paraphrased):
CSI Construction Specifications Practice Guide – description of the purpose of a specification section and SectionFormat (Parts 1–3) and the need to define relationships to other work.
CSI CDT Study Materials – guidance on what specifications should and should not include (no trade assignments, no costs, focus on requirements and coordination).
Cost classification, data organization, and specifications use which written formats?
OmniClass and UniFormat
UniFormat and MasterFormat
OmniClass and MasterFormat
SectionFormat® and MasterFormat
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI distinguishes among several written formats, each with a specific purpose:
UniFormat – organizes information by systems and assemblies (elements) and is commonly used for:
Cost classification and early cost estimating,
Data organization in the programming, schematic design, and design development stages.
MasterFormat – organizes information by work results (trades/products) and is used for:
Project specifications,
Detailed cost information tied to specification sections,
Organizing procurement and construction information.
CSI’s practice guides clearly connect cost classification and data organization in early design with UniFormat, and detailed specifications and later-stage cost information with MasterFormat. Therefore, the correct pair is:
UniFormat and MasterFormat (Option B)
Why the other options are incorrect:
A. OmniClass and UniFormat – OmniClass is a broader classification system for the built environment, not the primary written format CSI assigns to “specifications.” UniFormat is used for cost and systems, but OmniClass is not the standard format for specs.
C. OmniClass and MasterFormat – Again, OmniClass is overarching; it does not replace UniFormat as the main element-based cost classification tool.
D. SectionFormat and MasterFormat – SectionFormat is the internal three-part structure of a specification section (Parts 1, 2, and 3) and is not the format used for cost classification and data organization; that role is assigned to UniFormat.
Relevant CSI references (paraphrased):
CSI Project Delivery Practice Guide – descriptions of UniFormat use for system-based project descriptions and cost planning, and MasterFormat use for work result organization.
CSI Construction Specifications Practice Guide – chapters on MasterFormat, UniFormat, and their roles in specifications and estimating.
During procurement activities, what is the process of notifying prospective or qualified bidders requesting proposals for a specific project or issuing an invitation to bid?
Solicitation
Instructions for Procurement
Instructions to Bidders
Request for Scope of Work
In CSI and CDT terminology, the process of reaching out to potential or prequalified bidders to obtain bids or proposals is called “solicitation.”
The procurement (bidding) phase includes preparing procurement documents and then soliciting bids or proposals from interested or qualified firms.
“Solicitation” covers all methods used to notify and invite participation: advertisements, invitations to bid, requests for proposals (RFPs), and notices to prequalified bidders.
CSI’s Project Delivery Practice Guide and CDT study materials describe the sequence in the procurement stage roughly as:
Preparation of procurement documents (including Instructions to Bidders/Offerors, bid forms, proposed contract forms, etc.).
Solicitation of bids or proposals – announcement or direct issuance to prospective bidders.
Receipt, opening, and evaluation of bids/proposals.
Recommendation and award of contract.
Within that structure, “solicitation” is clearly identified as the step where the owner/AE issues the invitation to bid or request for proposals. The other answer choices refer to documents or requests that are part of the process, but not the process itself:
B. Instructions for Procurement – The CDT/CSI terminology is usually “Instructions to Bidders” or “Instructions to Offerors,” which are sections within the procurement documents explaining how to submit bids (time, place, format, required forms, etc.). They are not the act of announcing or inviting; they are a part of the documents used once solicitation has begun.
C. Instructions to Bidders – This is a specific document or section that sets the rules for bidding (bid security, withdrawal of bids, opening procedures, etc.). It is not the overall process of broadcasting the opportunity; instead it governs bidder behavior after solicitation has occurred.
D. Request for Scope of Work – This is not a standard CSI/CDT term. Scope of work is normally defined in the drawings, specifications, and sometimes in a statement of work, but “request for scope of work” is not used as the formal label for the invitation stage.
Because the question asks specifically for “the process of notifying prospective or qualified bidders requesting proposals for a specific project or an invitation to bid,” the correct CSI-aligned term is “Solicitation” (Option A).
Relevant CSI references (no URLs):
CSI Project Delivery Practice Guide – Procurement phase and terminology for solicitation of bids/proposals.
CSI Construction Specifications Practice Guide – Sections on procurement and bidding documents.
CSI CDT Body of Knowledge – Topic: Procurement (solicitation and receipt of bids/proposals).
Which document directly modifies the requirements of the general conditions?
Division 01, General Requirements
Supplementary Conditions
Agreement
Instructions to Bidders
In the standard organization of the contract documents as taught in CSI’s CDT materials and practice guides, the General Conditions establish the baseline contractual rights, responsibilities, and relationships among the owner, contractor, and architect/engineer (A/E).
CSI explains that whenever there is a need to change or add to the standard provisions of the General Conditions (for example, to address project-specific insurance limits, bonding, liquidated damages, or local legal requirements), those changes are made in the Supplementary Conditions. The Supplementary Conditions are expressly written to modify, delete, or add to the printed General Conditions, and they do so by direct reference to specific articles or paragraphs.
The General Conditions set the standard, overall rules of the contract.
The Supplementary Conditions are the only document whose primary purpose is to modify those General Conditions for the specific project.
Other documents (Agreement, Division 01) must be consistent with the Conditions of the Contract but are not the formal instrument intended to “directly modify” the General Conditions.
Why the other options are not correct:
A. Division 01, General Requirements – Division 01 coordinates administrative and procedural requirements for the work and bridges from the Conditions of the Contract to the technical specifications. It may elaborate how procedures are implemented but it is not the document that directly amends the General Conditions.
C. Agreement – The Agreement (e.g., AIA A101) identifies parties, contract sum, contract time, and incorporates the Conditions, drawings, and specifications by reference. It relies on the General and Supplementary Conditions; it does not systematically edit their language.
D. Instructions to Bidders – These govern the procurement phase only (how to submit bids, qualifications, bid security, etc.) and cease to have effect once the Contract is executed. They do not modify the General Conditions of the construction contract.
CSI’s Project Delivery and Construction Specifications Practice Guides describe this hierarchy and emphasize that Supplementary Conditions are the proper instrument for project-specific modifications to the General Conditions, which makes Option B the correct answer.
For a large transportation project, 53 borings were made and only one boring showed some contamination. Due to financial constraints, the owner is unable to provide additional funding to the design team for further investigation. Which of the following is the best course of action for the design team?
Withhold the information from the bid package because the full extent remains unknown. Ask bidders to provide a unit cost for remediation.
Provide a disclaimer on the contract documents about potential contaminants onsite and suggest the owner make the geotechnical report available to all bidders.
Insist the owner undertake additional investigation to determine the full extent prior to putting the project out for bid.
Proceed with design as is without any modifications since the results are statistically insignificant (i.e., well within expected deviations).
CSI’s project delivery and ethical guidance (as reflected in CDT materials and standard practice) emphasize:
Known information that may affect cost, risk, or safety must be disclosed consistently and fairly to all bidders.
The design professional must act in a manner that is honest, transparent, and protective of public safety, even when data is incomplete.
The bid documents should not conceal information that could materially affect the work, even if its full extent is uncertain.
Applying those principles:
The design team has evidence (one contaminated boring) that contamination may exist onsite. Even if the extent is unknown, that fact is potentially material to bidders (cost of remediation, handling of contaminated soils, schedule impacts).
The best course is to disclose what is known and ensure all bidders have access to the same geotechnical information. This is exactly what Option B proposes:
Place a clear note or disclaimer in the contract documents stating that contaminants were encountered in at least one boring and may be present elsewhere.
Recommend that the owner make the geotechnical report available to all bidders, so every bidder can evaluate the risk and price accordingly.
Why the other options are inconsistent with CSI-aligned practice:
A. Withhold the information… – Concealing known contamination is unethical and undermines fair bidding. Even with unit prices for remediation, bidders would be pricing blindly without knowing that contamination has already been detected.
C. Insist the owner undertake additional investigation… – While the design team should recommend further investigation, it cannot “insist” beyond professional advice, especially where the owner has clearly stated financial constraints. Regardless, disclosure of existing data is still required.
D. Proceed with design as is… – Ignoring known contamination and calling it “statistically insignificant” is not defensible; even one contaminated boring is important information that must be shared.
So, the most appropriate and CSI-consistent choice is Option B: disclose the potential and share the geotechnical report so all bidders are equally informed.
CSI references (by name only, no links):
CSI Project Delivery Practice Guide – sections on procurement, fair competition, and disclosure of information
CDT ethics and professional conduct principles regarding risk disclosure to bidders
Who is responsible for job site security?
Owner
Architect/engineer
Contractor
Construction manager
Under CSI’s project delivery framework and the typical General Conditions of the Contract, the contractor has primary responsibility for:
The means, methods, techniques, sequences, and procedures of construction.
Job site safety and security, including protection of workers, the public, and the work itself.
Controlling access to the site, securing materials and equipment, and complying with safety laws and regulations.
CSI’s CDT materials summarize the allocation of responsibilities this way (paraphrased):
The owner is responsible for providing information, funding, and overall project requirements; the owner does not direct day-to-day site operations or security.
The architect/engineer is responsible for design and contract administration functions such as reviewing submittals, certifying payments, and evaluating change requests—not for job site security or safety control.
The contractor (or construction manager acting as contractor, where applicable) is the party who controls the site and is therefore responsible for job site safety and security.
Even when a construction manager is involved (Option D), CSI and standard general conditions distinguish between a CM as advisor (who advises the owner) and a CM as constructor (who is essentially the contractor). For the exam-style question as written, “contractor” is the single correct generic answer for who is responsible for job site security.
Why the other options are not correct:
A. Owner – The owner does not direct means and methods or daily site activities; shifting site security responsibility to the owner would contradict the usual conditions of the contract.
B. Architect/engineer – The A/E does not control the job site and is not responsible for job site safety/security; this is a repeated CDT exam emphasis to avoid misallocating liability.
D. Construction manager – Only in specific project delivery methods where the CM is also the constructor (CM-at-Risk) does this role overlap with the contractor. The question’s general form points to the contractor as the standard answer in CSI’s framework.
Therefore, in accordance with CSI’s explanation of roles and responsibilities under standard conditions of the contract, the contractor is responsible for job site security, making Option C correct.
Which of the following is a scaled view?
Perspective
Foundation plan
Riser diagram
Isometric
In CSI-based drawing conventions, a scaled view is one drawn at a stated scale so that actual dimensions can be measured directly from the drawing (e.g., 1:100, 1/4" = 1'-0"). CSI’s Uniform Drawing System (UDS) treats floor plans, roof plans, and foundation plans as primary orthographic views prepared at a defined scale for dimensioning and coordination between disciplines. These are the standard “working drawings” for construction.
Foundation plan (Option B)A foundation plan is an orthographic plan view drawn to a specific scale showing footings, slabs, and foundations with dimensions and notes. It is intended for measurement and layout, and CSI references it as one of the basic scaled plan views of the project drawings.
Why the other options are not correct:
A. Perspective – Perspectives are pictorial views used for visualization and presentation. CSI notes that such views are typically not used for taking dimensions and may not be drawn to a true working scale.
C. Riser diagram – Riser diagrams (for plumbing, fire protection, electrical, etc.) are diagrammatic, showing relationships and routing, not physical locations at scale. They are expressly identified as “not to scale” in most construction document standards.
D. Isometric – Isometric drawings are a type of pictorial/axonometric view used to show three-dimensional relationships. While they can sometimes be constructed proportionally, CSI’s guidance treats them as diagrammatic/pictorial views rather than the primary scaled working views used for dimensioning work in the field.
CSI References (no links):
CSI Uniform Drawing System (UDS) modules on drawing types and views (plan, elevation, section, diagrammatic views).
CSI Project Delivery Practice Guide – discussion of scaled plan views as part of the construction documents set.
When the specifications allow controlled substitutions, a substitution may be approved during the bidding period only if what?
An addendum is issued to all the bidders
The proposer of the substitution is notified in writing
The architect/engineer accepts the substitution during the pre-bid meeting
Specifications are revised and reissued to include the substitution
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI emphasizes fairness, clarity, and equal information for all bidders. When controlled substitutions are permitted during bidding, the procedure typically described in Division 01 and the Instructions to Bidders is:
A bidder or manufacturer may propose a substitution for a specified product within a defined time before bid date.
The architect/engineer reviews the proposed substitution and may accept or reject it.
If the substitution is accepted, it must be communicated to all prospective bidders in a formal way so that every bidder is pricing the same requirements.
The correct formal mechanism during the bid period for changing procurement documents is an addendum. Therefore:
A substitution may be approved during bidding only if its approval is issued by an addendum to all bidders.
This maintains a level playing field and prevents one bidder from having a private advantage or a different scope basis than others.
Why the other options are not sufficient or correct alone:
B. The proposer of the substitution is notified in writingNotifying only the proposer does not put all bidders on the same basis. CSI stresses that changes affecting price, scope, or products must be distributed to all bidders via addenda during the procurement phase.
C. The architect/engineer accepts the substitution during the pre-bid meetingEven if verbally accepted in a pre-bid meeting, it must be officially documented by an addendum. Pre-bid meeting minutes alone are not a proper modification of the procurement documents unless they are explicitly issued as part of an addendum.
D. Specifications are revised and reissued to include the substitutionCompletely revising and reissuing specifications is not the usual or efficient method during a normal bid period. Instead, CSI practice is to use addenda to modify the existing specifications. On larger changes, an addendum may include revised pages, but the key formal instrument remains the addendum.
Therefore, in CSI-aligned bidding procedures, a substitution can be approved during bidding only when it is issued to all bidders as an addendum, making Option A the correct answer.
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – procurement process, bidder communications, and substitutions.
CSI Construction Specifications Practice Guide – Division 01 sections on Substitution Procedures and Instructions to Bidders regarding substitutions.
CSI CDT Study Materials – controlled substitutions during bidding and the role of addenda.
Which term or word is appropriate to use in specification text?
Any
As per
As required
Work
CSI’s Construction Specifications Practice Guide and CDT materials provide clear guidance on appropriate wording in specifications. They stress:
Use clear, specific, and enforceable language.
Avoid vague, subjective, or nontechnical terms that create ambiguity and open interpretation.
Among the answer choices, “Work” is the only word that is appropriate and standard in CSI-compliant specification text:
“Work” is a defined term in the General Conditions (and often Division 01), usually meaning the total construction and services required by the Contract Documents, including all labor, materials, equipment, and services necessary to complete the project.
Because it is defined and used consistently, “Work” is an acceptable and precise term for specification language. Example usage (conceptually): “Perform all Work in accordance with…”.
Why the other terms are inappropriate per CSI guidance:
A. AnyCSI recommends avoiding “any,” “either,” “etc.” and similar words because they are non-specific and create ambiguity. For example, “provide any fasteners as needed” does not clearly define what is required and can lead to disputes and inconsistent interpretation.
B. As perThe phrase “as per” is discouraged in CSI-style writing. It is considered informal and can be replaced by clearer, more direct phrasing such as “in accordance with,” “according to,” or “as indicated in.” CSI advocates for concise, plain, and unambiguous English in specs.
C. As requiredCSI strongly cautions against phrases like “as required” or “as necessary” when they are not tied to a clear condition or reference. They shift the decision to someone’s judgment later, instead of stating the requirement explicitly. If something is required, the specification should state what, when, and under what conditions, rather than simply saying “as required.”
Therefore, in a CSI-compliant specification, the term that is clearly appropriate from the options given is “Work” (Option D).
Relevant CSI references (no URLs):
CSI Construction Specifications Practice Guide – Chapters on language and writing style for specifications (clear, concise, complete, correct).
CSI Practice Guide for Principles & Formats of Specifications – Guidance on defined terms such as “Work.”
CSI CDT Body of Knowledge – Sections on specification-writing best practices and prohibited vague phrases.
What is the basis of payment for a contract negotiated between an owner and a contractor for a fixed price?
Stipulated sum
Unit price
Cost-plus-fee
Cost-plus-fee with guaranteed maximum price
CSI’s treatment of methods of payment / contract pricing (as used in standard owner–contractor agreements and CDT content) includes several common bases of payment:
Stipulated Sum (Lump Sum)
The contractor agrees to provide the work for a single fixed price.
The price does not change except through formal changes to the work (change orders).
This is the classic “fixed-price” contract form.
Unit Price
The contractor is paid based on measured quantities of work completed multiplied by agreed unit rates.
Final cost depends on actual quantities installed, not a single fixed total.
Cost-Plus-Fee
The owner reimburses actual cost of the work (labor, materials, equipment, etc.) plus a fee (fixed or percentage) as contractor’s compensation.
The final cost is not fixed; it varies with actual costs incurred.
Cost-Plus-Fee with Guaranteed Maximum Price (GMP)
A variation of cost-plus where the total reimbursable cost plus fee is capped at a guaranteed maximum.
Still not the same as a straightforward fixed lump sum; the basis is cost reimbursement up to a cap.
The question specifically asks: “for a fixed price.” In CSI and standard contract terminology, “fixed price” = “stipulated sum” (or lump sum). That is:
The owner and contractor negotiate a single dollar amount for the entire scope of work;
The contractor’s compensation is that stipulated sum, adjusted only by approved changes.
Why the other options are not correct:
B. Unit price – The total cost is not fixed at the time of contracting; it depends on actual installed quantities.
C. Cost-plus-fee – Costs are reimbursed; final price is open-ended and therefore not fixed.
D. Cost-plus-fee with guaranteed maximum price – This sets a cap, but the actual final cost is not a single fixed price; it is “actual cost plus fee” up to the GMP.
Therefore, the correct basis of payment for a fixed-price contract is Stipulated sum (Option A), consistent with CSI’s classification of contract types and standard owner–contractor agreements.
Key CSI References (titles only, no links):
CSI Project Delivery Practice Guide – sections on “Basis of Payment” and contract pricing methods (stipulated sum, unit price, cost-plus, GMP).
CSI CDT Body of Knowledge – Contract Types and Methods of Payment.
Standard owner–contractor agreements discussed in CSI materials (e.g., stipulated sum as the fixed-price form).
What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?
Building code
Quality control standard
Reference standard
Specification master
CSI’s terminology for specifications includes the concept of a “reference standard”, which is:
A requirement established by a recognized authority, by custom, or by general consensus.
An accepted criterion used to define properties, performance, or methods for materials, products, or workmanship (e.g., ASTM, ANSI, ACI, AISC, UL).
Cited in specifications so that, instead of repeating technical details, the spec simply references the named standard.
This is exactly the definition implied by the phrase “requirement set by authority, custom, or general consensus that is also an established accepted criterion.” That is the CSI definition of a standard, and in specification-writing context, specifically a reference standard. Hence the correct choice is C.
Why not the others:
A. Building code – A building code is a legal document adopted by public authority and enforced by the authority having jurisdiction; it is one type of regulatory document but not the generic term used in CSI for “established accepted criterion” used as a reference in specs.
B. Quality control standard – Quality control is a process; standards may be used within QC, but “quality control standard” is not the CSI term that matches this specific definition.
D. Specification master – CSI refers to master guide specifications or master specifications, but this is a spec-writing resource, not the formal term for a requirement established by authority or consensus.
CSI-aligned references (no URLs):
CSI Construction Specifications Practice Guide – explanations of standards and reference standard method of specifying.
CSI CDT Body of Knowledge – definitions of “standard” and “reference standard” in the context of specifications.
During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?
After the authorities having jurisdiction issues a permit
Closeout phase
Preconstruction phase
Construction phase
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI organizes the facility life cycle into phases such as planning, design, construction, closeout, and operations/occupancy. Within this framework, CSI describes project closeout as the phase where the contractor and design team complete all remaining contractual obligations and formally turn the project over to the owner.
A key part of that turnover is providing the owner with operations and maintenance (O&M) information, often including:
Operating and maintenance manuals for equipment and systems
Warranties and guarantees
Spare parts lists and recommended maintenance procedures
As-built/record documentation and, sometimes, commissioning records and training materials
CSI indicates that these O&M documents are to be delivered as part of the closeout requirements, usually at or near Substantial Completion or Final Completion, so that the owner can properly operate and maintain the facility during the occupancy phase.
Therefore the correct answer is B. Closeout phase.
Why the other options are incorrect:
A. After the authorities having jurisdiction issues a permitPermits are typically issued during design or preconstruction, authorizing the start of work. At this time, the facility is not built and O&M documentation does not yet exist in final form. CSI treats permits as part of regulatory approvals, not the turnover of maintenance information.
C. Preconstruction phasePreconstruction focuses on activities like finalizing construction documents, bidding, procurement planning, and initial mobilization. O&M manuals cannot be finalized because products and systems are not yet fully installed, tested, and accepted.
D. Construction phaseDuring construction, some O&M information may be started or submitted in draft form, but CSI’s guidance is clear that formal delivery of complete O&M documentation is a closeout requirement, not an in-progress construction requirement.
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – facility life cycle and project closeout chapters.
CSI Construction Specifications Practice Guide – Division 01 sections (Closeout Submittals, Operation and Maintenance Data).
CSI CDT Study Materials – topics on project closeout, warranties, and O&M documentation.
When developing an operation and maintenance (O&M) budget for a facility, what should form the basis for budget decisions?
The architect/engineer’s projected operating costs
The construction manager’s life cycle analysis
The estimator’s preliminary project description
The facility manager’s historical record of actual costs
CSI’s project-delivery and facility-management perspective emphasizes that O&M budgeting should be grounded in real, documented performance and cost history wherever possible. The facility manager is the team member who typically maintains:
Utility bills
Maintenance contracts and work orders
Repair and replacement histories
Staff, labor, and consumables costs
These form a historical record of actual O&M costs, which provides the most reliable basis for forecasting future O&M budgets.
Technical guidance on O&M cost analysis similarly stresses that:
Agencies “should maintain O&M cost records” that document baseline costs.
When defining an O&M cost baseline, it is recommended to use as much historical data as possible, and that historic O&M costs and actual site data should be used wherever possible.
Research on O&M budgeting practice has found that historical-based budgeting predominates among budgeting bases used in real facilities.
That is exactly what Option D describes: the facility manager’s historical record of actual costs is the correct and most defensible basis for making O&M budget decisions.
Why the others are less appropriate from a CSI/CDT standpoint:
A. Architect/engineer’s projected operating costs – A/E projections can be useful at early planning stages, but they are estimates, not verified costs. Once a facility has operating history, the A/E’s projections are secondary to actual cost data.
B. Construction manager’s life cycle analysis – Life-cycle cost analyses are valuable for choosing systems and strategies, but they are models and assumptions, not the primary budget baseline once real cost data exist.
C. Estimator’s preliminary project description – A Preliminary Project Description (PPD) is a design-stage estimating and scoping tool, not an operating-cost record. It has no direct tie to actual O&M performance.
Therefore, under CSI-aligned practice, the facility manager’s historical record of actual costs (Option D) is the correct basis.
Core CSI-aligned references for this question (no URLs):
CSI Project Delivery Practice Guide – chapters on facility management and life-cycle considerations.
DOE/FEMP guidance on O&M baselines and cost savings, stressing use of historic O&M cost data and actual site data.
Research on O&M budgeting showing predominance of historical-based budgeting.
Which team member is actively involved and interested in all phases of the project?
Contractors
Owners
Architects/engineers
Manufacturers/suppliers
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI’s project delivery framework places the owner at the center of the facility life cycle. The owner:
Initiates the project by defining needs and project goals.
Selects the project delivery method and engages the design and construction teams.
Participates in planning, design decisions, funding, and approvals.
During construction, the owner is responsible for payments, change decisions, and acceptance of the work.
After construction and closeout, the owner (often through a facility management group) is responsible for operation, maintenance, and long-term performance of the facility.
CSI repeatedly highlights that only the owner is engaged from the earliest concept through long-term operation and eventual renovation or disposal. All other parties (designers, contractors, manufacturers) participate for limited phases.
Therefore, the party “actively involved and interested in all phases of the project” is clearly:
B. Owners
Why the other options are incorrect:
A. ContractorsContractors typically become formally involved at procurement/bidding and remain through construction and closeout. They usually have no role in early planning (except in some delivery methods like CM-at-Risk or IPD where they join during design) and no long-term responsibility for operations beyond warranty obligations.
C. Architects/engineersThe A/E’s primary involvement is during planning and design, and then construction administration during construction and closeout. After the project is turned over, their involvement often ends unless separately engaged for post-occupancy evaluations or future work. They do not normally manage day-to-day operations and maintenance.
D. Manufacturers/suppliersManufacturers and suppliers participate mainly in product selection, submittals, and furnishing materials and equipment during design-assist and construction phases. They may have continuing obligations for warranties or support, but they are not engaged in every phase of the project’s life cycle as the owner is.
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – roles and responsibilities of the owner, design professional, contractor, and others.
CSI Facility Management Practice Guide – owner’s role during operations and the extended facility life cycle.
CSI CDT Study Materials – diagrams and explanations of project participants over the facility life cycle.
Which is the reference document that includes guidelines and tools for the organization and presentation of design and construction drawings?
AIA CAD Layer Guidelines
National Institute of Building Sciences
National BIM Standard – United States
U.S. National CAD Standard
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
Within CSI’s CDT framework, the primary national reference for organizing and presenting design and construction drawings is the U.S. National CAD Standard (NCS). The NCS is a coordinated standard developed by several organizations including the National Institute of Building Sciences (NIBS), CSI, and the AIA. It provides:
Guidelines for drawing sheet organization (titles, numbering, and content).
Layering standards (including what many people know as the AIA CAD Layer Guidelines).
Symbols, plotting conventions, and other tools that make drawings consistent and coordinated across disciplines and projects.
CSI’s project delivery and documentation guidance points design professionals and specifiers to the U.S. National CAD Standard as the key reference for how drawings should be structured and presented to support clear coordination with specifications and other contract documents.
Why the other options are not the best answer:
A. AIA CAD Layer GuidelinesThese guidelines are actually a component of the U.S. National CAD Standard, primarily addressing layer naming and organization. On their own they do not provide the full system for sheet organization, plotting, and cross-discipline coordination that the question describes. CSI and NIBS treat them as part of the broader NCS.
B. National Institute of Building SciencesNIBS is an organization, not the actual “reference document.” NIBS sponsors and publishes several standards (including the NCS and the National BIM Standard–US), but the question asks specifically for the document that includes the guidelines and tools for drawing organization and presentation. That document is the U.S. National CAD Standard, not NIBS itself.
C. National BIM Standard – United StatesThe National BIM Standard–US focuses on BIM information exchange, modeling protocols, data structures, and interoperability, not on the traditional CAD sheet organization and 2D drawing presentation. It is important, but it is not the primary reference CSI cites for the organization and presentation of drawings in the traditional contract documents sense.
Therefore, consistent with CSI CDT content, the correct answer is Option D: U.S. National CAD Standard.
CSI reference concepts:
CSI Project Delivery Practice Guide – sections on construction documents and the role of standards such as the U.S. National CAD Standard in organizing drawings.
CSI CDT body of knowledge – topics on drawing organization, coordination between drawings and specifications, and national CAD standards.
Within the context of the construction industry, what does BIM stand for?
Building Information Modeling
Business Information Manual
Building Interior Maintenance
Building Inspection Manual
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI’s project delivery and documentation discussions, BIM is consistently defined as “Building Information Modeling.”
CSI describes BIM as:
A digital representation of the physical and functional characteristics of a facility.
A shared knowledge resource for information about a facility, forming a reliable basis for decisions during its life cycle.
A tool that supports coordination, clash detection, documentation, quantity takeoff, and communication between design and construction team members.
BIM models are used alongside, and coordinated with, drawings, specifications, and other contract documents, and they support communication and decision-making throughout design, construction, and sometimes operation.
The other options are not recognized industry meanings of BIM:
B. Business Information Manual – not a standard construction-industry term.
C. Building Interior Maintenance – does not match CSI or industry definitions of BIM.
D. Building Inspection Manual – again, not the accepted meaning of BIM in the AEC context.
Therefore, in the construction context, BIM stands for “Building Information Modeling” (Option A).
Key CSI References (titles only):
CSI Project Delivery Practice Guide – chapters addressing BIM and information management.
CSI Construction Specifications Practice Guide – discussions of model-based delivery and coordination with specifications.
CSI CDT Body of Knowledge – terminology and emerging practices including BIM.
The owner's budget may not be adequate to pay for the entire project. What method is used to allow flexibility in the event that the budget is exceeded by the bids?
Cash allowance
Quantity allowance
Unit pricing
Alternates
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI describes several techniques in the procurement documents to manage cost uncertainty. When the owner is concerned that the project may exceed the budget when bids are received, the most common tool to allow scope flexibility is the use of alternates.
Alternates (often called “bid alternates”):
Are defined variations in the work (additions or deletions) that bidders price separately from the base bid.
Can be additive (additional scope that can be accepted if the budget allows) or deductive (scope that can be removed to reduce cost if needed).
Give the owner the ability, after seeing the base bids, to accept or reject alternates to bring the project within the available budget without redesigning the entire project.
This fits the scenario in the question exactly: the owner anticipates that the budget may be tight and wants a mechanism to adjust the final contract amount if bids come in high.
Why the other options are not the primary CSI method for this budget-flexibility issue:
A. Cash allowanceAn allowance is a set amount included in the contract sum to cover a defined but not fully specified portion of the work (e.g., artwork, specialty items). It helps manage scope uncertainty, but it doesn’t systematically provide a way to reduce overall cost after bids in the same way alternates do.
B. Quantity allowanceThis is a form of allowance tied to a presumed quantity (e.g., rock excavation). It addresses uncertain quantities, not overall budget flexibility in the bidding process.
C. Unit pricingUnit prices provide fixed prices per unit (e.g., per cubic meter, per square meter) for work items whose final quantities are uncertain. They are useful for adjustments after contract award as quantities change, but they are not the primary tool for adjusting total scope to meet the owner’s budget at bid time.
Therefore, the CSI-aligned answer for allowing flexibility when bids may exceed the budget is:
D. Alternates
Key CSI-Related References (titles only, no links):
CSI Project Delivery Practice Guide – procurement and pricing strategies, including alternates and allowances.
CSI Construction Specifications Practice Guide – Division 01 sections on Alternates, Unit Prices, and Allowances.
CSI CDT Study Materials – explanations of bid alternates and their role in controlling project cost.
What project scheduling technique involves setting the target date of building occupancy and then working backwards to establish preceding milestone dates?
Methods technique
Critical path method
Front end loading
Schedule of values
CSI’s project delivery and scheduling discussions describe network scheduling techniques such as the Critical Path Method (CPM) as tools for planning, sequencing, and controlling project time. CPM scheduling can be done either:
Forward, starting from a known start date and computing early and late completion dates, or
Backward, starting from a required completion/occupancy date and working backward to determine the latest allowable dates for preceding activities and milestones so that the final completion date is achieved.
This “working backward from a target completion or occupancy date to set milestone dates” is a classic application of the backward pass within the Critical Path Method. CSI’s project management materials emphasize that CPM is used to:
Establish logic relationships and durations,
Calculate early and late start/finish dates,
Identify the critical path, and
Adjust the schedule to meet a required completion or occupancy date by compressing or resequencing activities where possible.
Why the other options are not correct:
A. Methods technique – This is not a standard CSI or mainstream term for a recognized scheduling method.
C. Front end loading – In project management and cost engineering usage, this refers to investing significant effort early in project definition and planning; it is not specifically defined as the technique of back-scheduling from an occupancy date.
D. Schedule of values – This is a cost-allocation and payment document that breaks the contract sum into portions for progress payments. It is not a scheduling technique.
Because CPM scheduling explicitly supports setting a required completion date and then working backward to develop realistic milestone dates and activity sequencing, Option B – Critical path method is the best and CSI-consistent answer.
A facility manager needs to replace a broken insulated glazing unit in an existing facility. Which source would be most appropriate for determining where and how to order the new unit?
Record drawings
Manufacturer's representative
Project manual
Record submittals
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI’s guidance on project record documents distinguishes between several types:
Record drawings – show what was actually installed (dimensions, locations, configurations).
Record specifications/project manual – the written requirements for the work, as issued and modified.
Record submittals – approved shop drawings, product data, and samples documenting the actual products and systems installed, including manufacturer names, model numbers, finishes, and installation instructions.
For replacement of a specific product, such as a broken insulated glazing unit, CSI instruction is that the most precise source is record submittals (Option D). These typically contain:
The exact manufacturer selected.
Product line, model number, glass type, coatings, spacers, gas fill, etc.
Any special fabrication notes or custom sizes.
Contact information or catalog data to facilitate reordering.
This is exactly the information a facility manager needs to “determine where and how to order” the replacement unit. That is why CSI emphasizes maintaining record submittals as part of the owner’s permanent facility information.
Why the other options are less appropriate:
A. Record drawingsRecord drawings (sometimes called “as-built” drawings) can provide size and location of the glazing unit, and possibly indicate type (e.g., “insulated glazing unit”). However, drawings rarely show the precise product manufacturer and model; at best, they reference detail markers or generic notes. They are helpful for field measurement and coordination, but not ideal for identifying the exact product to order.
B. Manufacturer’s representativeA manufacturer’s rep can help once you know the manufacturer and product, but first you need to identify which manufacturer and model were actually installed. Without the record submittals or similar documentation, the rep would be guessing. CSI places the identification of the installed product squarely in the realm of record submittals.
C. Project manualThe project manual (including the specifications) usually lists acceptable manufacturers and products, or performance requirements, but it does not necessarily tell you which one was actually used. If multiple manufacturers or options were permitted, the project manual alone cannot identify the exact unit to reorder.
Thus, under CSI’s treatment of project record documents and facility information, record submittals (Option D) are the best and most appropriate source for ordering an exact replacement product.
CSI reference concepts:
CSI Project Delivery Practice Guide – sections on “Project Closeout” and “Record Documents,” explaining the distinct roles of record drawings and record submittals.
CSI CDT Study Materials – topics describing record submittals as the owner’s record of actual installed products, used for maintenance and replacement.
When should a post-occupancy evaluation by the facility manager be performed?
At the end of the correction period
Three to six months after initial occupancy
Just before the end of the warranty period
One year after substantial completion
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
CSI describes post-occupancy evaluation (POE) as a review of how the completed facility is performing for its users and operations staff, compared to the Owner’s Project Requirements (OPR). For the evaluation to be meaningful:
The facility must have been occupied long enough for systems and spaces to be used under normal operating conditions.
It should happen early enough that findings can inform warranty corrections, adjustments, and future projects.
CSI’s practice guidance indicates that POEs are typically performed several months after initial occupancy, often in the range of three to six months, when occupants have adjusted to the building and operational patterns are established but the project is still within the correction/warranty period. That aligns with Option B.
Why the others are less suitable:
A. At the end of the correction period and C. Just before the end of the warranty period – these are usually around one year; waiting this long reduces the time available to act on findings while warranties are in force.
D. One year after substantial completion – also generally coincides with warranty expiration; by then, significant issues may have already affected operations without being captured early.
Relevant CSI references:
CSI Project Delivery Practice Guide – sections on facility management, occupancy, and post-occupancy evaluation.
CSI CDT Body of Knowledge – material on owner and facility manager activities during occupancy.
How long after bid opening is a bidder required to honor their bid price for a project?
It should be no less than the time period acknowledged on the bid form.
The time period is thirty days for a private project and indefinitely for a public project.
The time period should conform to requirements set by the Associated General Contractors of America.
The time period as established by the contract for construction.
In CSI’s procurement framework, the bidding documents (especially the Instructions to Bidders and the Bid Form) specify the time period during which a bid must remain open and may not be withdrawn.
CSI emphasizes:
The bid is an offer by the bidder, and the bidding documents define how long that offer is to remain valid.
This period is stated in the bidding requirements, and bidders acknowledge it by signing and submitting the bid form.
Common durations (e.g., 30, 60, or 90 days) are project-specific and are not fixed universally by CSI or any trade association.
Therefore, a bidder is required to honor their bid for no less than the time period that is explicitly stated and acknowledged on the bid form and in the bidding requirements, which corresponds to Option A.
Why the other options are incorrect:
B. Thirty days for private projects and indefinitely for public projectsCSI does not set such a rule. Both public and private owners typically state a specific time limit in the bidding documents. Public contracts often have statutory or policy-based periods, but never “indefinitely.”
C. Requirements set by the Associated General Contractors of AmericaAGC publishes standard forms and guidance, but the binding requirement for bid validity comes from the owner’s bidding documents, not from AGC’s generic recommendations.
D. As established by the contract for constructionAt the time of bidding, there is no executed construction contract yet. The bid validity period must be set before the contract is formed, in the bidding documents themselves. The construction contract applies only after the bid is accepted.
Key CSI Reference Titles (no links):
CSI Project Delivery Practice Guide – Procurement Phase, “Instructions to Bidders” and “Bid Form.”
CSI Construction Specifications Practice Guide – Bidding requirements and bid validity.
CDT Body of Knowledge – “Bidding and Negotiation; Contractor Selection.”
Standards for sustainable facilities, products, and fundamental approaches emphasize the needs of what?
Architect, supplier, and contractor
Owner, stakeholders, and participants
Public, private, and environmental health
Owner team, contractor team, and design team
CSI’s treatment of sustainability—as reflected in CDT materials and related practice guides—aligns with widely recognized sustainability concepts: construction and building standards should protect human health, the environment, and the welfare of the broader community (public).
Sustainability-related texts (including green building rating systems, green product standards, and sustainability sections in specifications) consistently emphasize:
Protection of human (occupant/public) health and safety,
Protection and enhancement of environmental quality,
Responsible use of resources and reduction of negative impacts over the facility life cycle.
Within that framework, standards for sustainable facilities and products are not primarily written around the preferences of a particular project team (like architect, contractor, or owner team). Instead, they are driven by the broader need to safeguard public and private users’ health and environmental health.
Thus, among the options provided:
C. Public, private, and environmental health is the only choice that reflects that sustainability standards focus on health and welfare of people and the environment, which is consistent with CSI’s project-delivery and specification guidance.
Why the other options are not correct in CSI context:
A. Architect, supplier, and contractorThese are project participants, not the underlying “needs” that sustainability standards are written to protect. Sustainable standards may affect their work, but the ultimate emphasis is on health, safety, and environmental impact, not on the interests of these parties themselves.
B. Owner, stakeholders, and participantsWhile owners and stakeholders are important in defining project requirements and may have sustainability goals, the standards themselves focus on performance outcomes like reduced environmental impacts and improved health and safety, rather than simply serving stakeholders’ preferences.
D. Owner team, contractor team, and design teamAgain, these are roles on the project. Sustainable standards are not framed around serving these teams’ “needs,” but around protecting people and the environment and achieving long-term performance.
In CSI-aligned specification practice, sustainability-related requirements are often placed in:
Division 01 sections (e.g., “Sustainable Design Requirements,” “Environmental Requirements”), and
Appropriate technical sections (Part 1 – general, Part 2 – products, Part 3 – execution),
and are tied to environmental and health outcomes, aligning with Option C.
Relevant CSI references (no URLs):
CSI Project Delivery Practice Guide – Sustainability and life-cycle considerations in project delivery.
CSI Construction Specifications Practice Guide – Guidance on specifying sustainable requirements and environmental performance.
CSI CDT Body of Knowledge – Sustainability and environmental considerations in construction documentation.
Copyright © 2021-2026 CertsTopics. All Rights Reserved