Question 25

What requirement is set by authority, custom, or general consensus that is also an established accepted criterion?

Options:

A.

Building code

B.

Quality control standard

C.

Reference standard

D.

Specification master

Question 26

During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?

Options:

A.

After the authorities having jurisdiction issues a permit

B.

Closeout phase

C.

Preconstruction phase

D.

Construction phase

Question 27

When developing an operation and maintenance (O&M) budget for a facility, what should form the basis for budget decisions?

Options:

A.

The architect/engineer’s projected operating costs

B.

The construction manager’s life cycle analysis

C.

The estimator’s preliminary project description

D.

The facility manager’s historical record of actual costs

Question 28

Which team member is actively involved and interested in all phases of the project?

Options:

A.

Contractors

B.

Owners

C.

Architects/engineers

D.

Manufacturers/suppliers