One of the significant differences between qualitative and semi-quantitative COF analysis for RBI is that the results of a semi-quantitative analysis are usually:
Who shall be responsible for assessing the types of damage mechanisms and their applicability and severity to the equipment?
An iso-risk line on a risk plot is a line:
Risk mitigation is defined as:
Which of the following statements is accurate regarding data quality relative to the type of RBI assessment selected?
The continuum of RBI approaches is the:
One of the key elements of an inspection plan is:
When equipment has deteriorated to such an extent that the risk of failure cannot be managed and held to an acceptable level, often the only way to mitigate risk is to:
Which of the following would be the minimum expectations of contractors hired to implement an RBI program?
Risk assessment is defined as the:
Once organizing the work process for RBI program planning has been completed, the next step is the identification of the:
What does sensitivity analysis typically involve?
How important is data quality in RBI assessment?
Which of the following codes provide requirements and limitations for implementing RBI programs? (Select all that apply)
The resources and time required to implement an RBI assessment will vary widely between organizations depending on a number of factors including:
Which of the following has the most direct relation to the relative accuracy of the RBI analysis?
Which of the following may make it impractical to reduce some risks to an acceptable level?
Which aspect of risk assessment is common to all types and levels of RBI?
What method of mitigation is most likely to reduce the amount and rate of release?
Why is it important to understand the difference between RBI accuracy and RBI precision?
Detailed information and data are needed for quantitative RBI in order to:
Depending on factors such as the remaining life of the equipment and the type of damage mechanism, risk management through inspection:
Inspection alone cannot adequately manage risk for equipment:
In preparing for a future inspection, which of the following assessments can be used to determine what flaws would require repair or replacement?
RBI plans identify equipment that does not require inspection or some other form of mitigation because of the acceptable level of risk associated with the equipment's current operation. In this way, inspection and maintenance activities can be:
Which of the following statements is correct with regard to the potential reduction of inspection cost by using RBI?
What is a risk driver?