Month End Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Adobe AD0-E903 Exam With Confidence Using Practice Dumps

Exam Code:
AD0-E903
Exam Name:
Adobe Workfront Project Manager Professional
Certification:
Vendor:
Questions:
70
Last Updated:
Apr 30, 2025
Exam Status:
Stable
Adobe AD0-E903

AD0-E903: Adobe Workfront Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the Adobe AD0-E903 (Adobe Workfront Project Manager Professional) exam? Download the most recent Adobe AD0-E903 braindumps with answers that are 100% real. After downloading the Adobe AD0-E903 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the Adobe AD0-E903 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the Adobe AD0-E903 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (Adobe Workfront Project Manager Professional) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA AD0-E903 test is available at CertsTopics. Before purchasing it, you can also see the Adobe AD0-E903 practice exam demo.

Adobe Workfront Project Manager Professional Questions and Answers

Question 1

What occurs when an individual enters a new commit date that is after the original planned date of a task?

Options:

A.

The assignee of any task that has the original task set as a predecessor is notified.

B.

The Project Owner is notified whether this change will impact the Project Timeline.

C.

The Planned Completion Date of the task automatically changes to match the new Commit Date.

Buy Now
Question 2

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

Options:

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select "Show the Milestone view on the Details tab."

Question 3

The last 5 tasks in a project need to happen within 10 days of the end of the project.

Which Task Constraint should the project manager use to configure this timeline without setting specific dates?

Options:

A.

Start No Later Than

B.

Must Start On

C.

As Late As Possible