Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

SAP Certified Application Associate C_TPLM22_67 Passing Score

Page: 4 / 6
Total 165 questions

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 Questions and Answers

Question 13

What are the different options available for project stock?

There are 3 correct answers to this question.

Response:

Options:

A.

No project stock

B.

Valuated project stock

C.

Non-valuated project stock

D.

WBS project stock

Question 14

Which of the following scenario doesn’t allow the plan value of the order to be added to the committed value of the WBS element until the order has the status released?

Please choose the correct answer.

Response:

Options:

A.

The funds commitment in plan indicators is set

B.

The funds commitment in plan indicator is not set

C.

The funds commitment in plan indicator is set to value less than 0

D.

The funds commitment in plan indicator also has status released

Question 15

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?

There are 3 correct answers to this question.

Response:

Options:

A.

Scheduling must have been carried

B.

A distribution key must be maintained in the work center

C.

A work center must be maintained in the activity

D.

The capacity requirements indicator must not be set in the network header

Question 16

What is the procurement element for requirements planning?

Please choose the correct answer.

Response:

Options:

A.

Purchase requisition

B.

Purchase order

C.

Procurement plan

D.

Planned order

Page: 4 / 6
Total 165 questions