Question 13

What is the correct sequence of the ASAP methodology phases?

Options:

A.

Project Preparation -> Business Blueprint -> Realization -> Training -> Go Live Support -> Run

B.

Project Launch -> Requirements and Design -> Build -> Go Live -> Run -> Optimization

C.

Project Preparation -> Business Blueprint -> Realization -> Final Preparation -> Go Live Support -> Run

D.

Plan Project -> Design Solution -> Build Solution -> Test -> Hand Over to IT -> Operate

Question 14

How can you achieve periodic controlling when a lot size based production scenario is used by logistics? (Choose two)

Options:

A.

Adjust the default rule in the default values for the production order type.

B.

Use an internal order in addition to the production order.

C.

Use a product cost collector in addition to the production order.

D.

Adjust the costing type of the plan costing variant.

Question 15

In customization for costing based CO-PA we assign costs and revenues to the required value field. Match the following sources of value fields.

1 Cost Estimate i. Fixed Cost of Goods Manufactured

2 WBS Elements ii. Freight costs

3 General ledger Posting iii. Research & development costs

4 Production order iv. Estimated bonuses

5 Additional costs v. Production Variances

Please choose the correct answer.

Response:

Options:

A.

1-i., 2-iii.,3-ii.,4-v.,5-iv.

B.

1-iv., 2-ii.,3-iii.,4-v.,5-i.

C.

1-ii.,2-iii.,3-i.,4-v.,5-iv.

D.

1-v., 2-iii.,3-ii.,4-v.,5-i

Question 16

Which data do you need to set up an accrual calculation with the percentage method? (Choose two)

Options:

A.

Accrual settlement rules with percentage method.

B.

Secondary cost element (category 31) as accrual cost element.

C.

Primary cost element (category 3) as accrual cost element.

D.

Accrual allocation cycle with sender receiver segments.

E.

Cost center or internal order (order category 2) as credit object.