Question 29

Universal Containers (UC) has multiple teams with major projects working concurrently in their own developer sandboxes. After deploying to production, a bug is discovered. Due to tight timelines, the development team has suggested correcting the bug in the user acceptance testing (UAT) environment, which is a full copy sandbox.

What should the architect recommend?

Options:

A.

UC should spin up a new sandbox to use as a hot fix environment. Once the bug is corrected, the change should be applied to production and downstream environments.

B.

The fix should be made in the developer environment where the project work was done. Once the fix has been made, it should go through a full deployment/testing process and adhere to the normal project cadence.

C.

Since the issue was found in production, it should be treated as a change request and go into the backlog as an enhancement.

D.

Correcting the bug in UAT is ideal. Since UAT is a full copy, it will be the fastest location to fix and test the resolution.

Question 30

Universal Containers (UC) is embarked on a large Salesforce transformation journey, UC ' s DevOps team raised a question about tracking Salesforce metadata throughout the development lifecycle across sandboxes all the way to production.

As the deployment architect of the project, what should be the recommendation to track which version of each feature in different environments?

Options:

A.

Use Salesforce SFDX commands to deploy to different sandboxes.

B.

Use an Excel sheet to track deployment steps and document the SFDX commands.

C.

Use an AppExchange or third-party tool that is specialized in Salesforce deployment.

D.

Use ChangeSet to track deployed customizations.

Question 31

An architect has been working on a large project for the past 6 months. This project must be live by the end of the current month.

Which two planning techniques should the architect use to ensure all metadata changes deploy smoothly and on time? Choose 2 answers

Options:

A.

Create a new sandbox and perform a test deployment to that environment.

B.

Ensure all code that is being deployed is checked into source control.

C.

Upload a change set from sandbox to production as early as possible.

D.

Validate the final deployment package against production prior to go-live

Question 32

Universal Containers is adopting Scrum as an agile methodology and wants to choose a software tool to support the adoption.

What three key features of an agile development support tool should an architect look for? Choose 3 answers

Options:

A.

Product backlog prioritization

B.

Sprint backlog management

C.

Work (for example, user stories or tasks) assignment

D.

Kanban board

E.

Email notifications when work is created or changed