Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Project+ PK0-004 Reddit Questions

Page: 17 / 30
Total 796 questions

CompTIA Project+ Exam Questions and Answers

Question 65

The design team and development team disagree about what technology should be used for a major requirement. A brainstorming meeting takes place, where both teams focus on the mutually agreed-upon deliverables.

Which of the following conflict resolution techniques did the teams use?

Options:

A.

Compromising

B.

Smoothing

C.

Confronting

D.

Forcing

Question 66

A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?

Options:

A.

Process diagram

B.

Change control plan

C.

Balanced scorecard

D.

SWOT matrix

Question 67

Which of the following primary factors are used to prioritize the development of risk response strategies?

(Choose two.)

Options:

A.

Likelihood

B.

Timeline

C.

Impact

D.

Quality

E.

Cost

Question 68

A new project manager is working in an environment where resources report to another supervisor. The

project manager is having difficulty with a particular member and wants to escalate the issue. Which of the

following documents should the project manager consult?

Options:

A.

Issue log

B.

RACI chart

C.

Risk management plan

D.

Organizational chart

Page: 17 / 30
Total 796 questions