PRINCE2 Prince2-Foundation Actual Questions

PRINCE2 Foundation Exam Questions and Answers

Question 13

Which is a purpose of the Closing a Project process?

Options:

A.

Authorize the final stage of the project

B.

Confirm that all benefits defined in the Business Case have been achieved

C.

Recognize whether objectives set out in the original Project Initiation Documentation have been achieved

D.

Delegate day-to-day management of the end of the project to the Project Manager

Question 14

In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

Options:

A.

Product Description

B.

Team Plan

C.

Work Package

D.

Stage Plan

Question 15

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

Options:

A.

Capture

B.

Examine

C.

Propose

D.

Decide

Question 16

Which is an objective of the Closing a Project process?

Options:

A.

Prepare the plan for the next stage

B.

Assess any benefits that have already been realized

C.

Produce a Benefits Review Plan to identify what benefits are expected

D.

Check that all benefits are realized before closing a project