Question 29

What process provides the information required to decide whether to authorize the delivery of a project?

Options:

A.

Directing a Project

B.

Initiating a Project

C.

Managing Product Delivery

D.

Starting up a Project

Question 30

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

Options:

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Question 31

During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?

Options:

A.

Benefits Review Plan

B.

Product Status Account

C.

Business Case

D.

Project Plan

Question 32

What theme establishes the mechanisms to judge whether a project is worthwhile investing in?

Options:

A.

Plans

B.

Business Case

C.

Risk

D.

Quality

Page: 8 / 9