PRINCE2 Foundation Questions and Answers

Question 13

Which role is part of the Project Board?

Options:

A.

Corporate or programme management

B.

Risk owner

C.

Project Manager

D.

Senior Supplier

Question 14

Identify the missing word in the following sentence.

The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

Options:

A.

activities

B.

processes

C.

products

D.

quality

Question 15

Which is NOT a true statement about the Managing a Stage Boundary process?

Options:

A.

It provides sufficient information for the Project Board to review the success of the current stage

B.

It is used to create an Exception Plan if requested by the Project Board

C.

It provides a fixed point at which acceptance of the project product is confirmed

D.

It is executed at, or close to, the end of each management stage, except the final one

Question 16

Which of the following are true statements about a Project Brief?

1. Used to provide a foundation for the Initiating a Project process

2. Created in the Starting up a Project process

3. Used by the Project Board to make an assessment of a project's progress

4. Used as the basis of the Project Initiation Documentation

Options:

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4