NVIDIA-Certified Professional NCP-AII Updated Exam

Page: 7 / 9
Total 123 questions

NVIDIA AI Infrastructure Questions and Answers

Question 25

After updating BlueField-3 DPU BMC firmware via Redfish, the engineer observes “TaskState: Running” but no progress after 15 minutes. How should they track the update’s completion status?

Options:

A.

Check /var/log/messages on the DPU operating system for update logs.

B.

Query the DPU BMC with the Task ID of the installation process.

C.

Power cycle the DPU immediately to force a rollback.

D.

Run bfrec --status on the DPU to view flash progress.

Question 26

A customer has just completed the first boot of their DGX system and is prompted to create an administrative user. What is the correct approach for setting up this user to ensure secure BMC and GRUB access?

Options:

A.

Create a unique, strong, lower-case username and password that will be used for both BMC and GRUB access, avoiding default or weak credentials.

B.

Create separate usernames for BMC and GRUB to maximize flexibility.

C.

Skip the creation of a new user and retain the default admin account for BMC and GRUB access.

D.

Use “sysadmin” as the username and a simple password for ease of management.

Question 27

A single-node stress test fails during the PCIe bandwidth validation phase. Which troubleshooting step is recommended first?

Options:

A.

Reduce PCIe Gen4 speed to Gen3 speed in BIOS settings.

B.

Reseat the GPU, then rerun the test.

C.

Disable NVLink in BIOS to isolate PCIe performance.

D.

Reinstall NVIDIA drivers using apt-get install nvidia-driver-550.

Question 28

During cluster validation, the Cable Validation Tool (CVT) reports " Underperforming (BER) " for an InfiniBand link. Which BER thresholds indicate a critical signal quality issue requiring cable replacement?

Options:

A.

Rx power variance > 3dB between lanes

B.

Effective BER > 0 during the first 125 minutes of link operation

C.

Raw BER > 1e-12 or Effective BER > 1.5E-254 for < 6hr measurements

D.

Temperature > 85°C on transceiver module

Page: 7 / 9
Total 123 questions