The correct answers are B, C, and D because they represent clear indicators of deficiencies in the Mechanical Integrity (Asset Integrity) program , as defined by CCPS.
Option B is correct because outdated metrics (9 months old) indicate poor performance monitoring and lack of timely oversight . CCPS stresses that asset integrity programs must use current, accurate data to track inspection, testing, and maintenance effectiveness.
Option C is also correct because excessive vibration in rotating equipment is a well-known sign of potential mechanical failure, such as imbalance, misalignment, or bearing issues. This suggests inadequate condition monitoring or maintenance practices.
Option D is critical because piping containing hazardous materials that is not included in inspection programs represents a serious gap. CCPS requires that all critical equipment be identified, risk-ranked, and included in inspection and maintenance plans . Missing such equipment indicates a breakdown in the integrity management system.
Option A reflects good practice, showing operator awareness and effective communication, not a problem.
Overall, CCPS emphasizes that effective asset integrity programs require accurate tracking, proactive monitoring, and comprehensive equipment coverage to prevent loss of containment.