Question 13

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

Options:

A.

When the Product Owner identifies new work.

B.

As soon as possible after they are identified.

C.

When the Scrum Master has time to enter them.

D.

During the Daily Scrum after the Development Team approves them.

Question 14

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

Options:

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

Question 15

When multiple teams work together on the same product, each team should maintain a separate Product Backlog.

Options:

A.

True

B.

False

Question 16

Which of the following is a Developer accountable for? (Choose the best two answers.)

Options:

A.

Selecting the Product Owner.

B.

Reporting productivity.

C.

Creating a plan for the Sprint, the Sprint Backlog.

D.

Organizing the work required to meet the Sprint Goal.