Question 25

Which product describes the roles and responsibilities for achieving the effective management of anticipated threats and opportunities in a project?

Options:

A.

Quality Management Strategy

B.

Risk Management Strategy

C.

Communication Management Strategy

D.

Configuration Management Strategy

Question 26

During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?

Options:

A.

Benefits Review Plan

B.

Product Status Account

C.

Business Case

D.

Project Plan

Question 27

Identify the missing words in the following sentence.

When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.

Options:

A.

Configuration Item Records

B.

Business Case

C.

Project Brief

D.

project management team and/or role descriptions

Question 28

Which is a purpose of the Organization theme?

Options:

A.

Ensure that the project organization structure will enable the project to deliver the business benefits in the required time frame

B.

Define accountability within the project

C.

Identify risk owners for the project

D.

Define the quality methods and responsibilities for the management of the project

Page: 7 / 11