Question 13

What is the maximum distance allowed below the design flood elevation from which ventilation may be obtained?

Options:

A.

0 inches

B.

6 inches

C.

1 foot

D.

2 feet

Question 14

When a permit is issued, the code requires that one set of approved plans and specifications be returned to the applicant.

This set of plans and specifications shall be:

Options:

A.

kept on the building site.

B.

returned to the architect.

C.

filed with the county clerk or jurisdiction to properly record the property.

D.

retained by the applicant for at least one year after the job is finished in the event modifications are made.

Question 15

When a furnace is installed in a 66-inch-high attic, the maximum distance from the passageway access to the furnace shall be _____ ft., measured along the centerline of the passageway.

Options:

A.

10

B.

15

C.

20

D.

50