Question 5

Which of the following are true statements about a Project Brief?

1. Used to provide a foundation for the Initiating a Project process

2. Created in the Starting up a Project process

3. Used by the Project Board to make an assessment of a project's progress

4. Used as the basis of the Project Initiation Documentation

Options:

A.

1, 2, 3

B.

1, 2, 4

C.

1, 3, 4

D.

2, 3, 4

Question 6

Who does the Team Manager report to and take direction from?

Options:

A.

Project Board

B.

Project Assurance

C.

Project Manager

D.

Project Support

Question 7

Which is a purpose of the Directing a Project process?

Options:

A.

Create and authorize the project mandate

B.

Ensure that work on products allocated to the team is authorized and agreed

C.

Control the day-to-day running of the project

D.

Delegate day-to-day management of the project to the Project Manager

Question 8

Which is a true statement about PRINCE2 event-driven controls

Options:

A.

Event-driven controls take place at predefined periodicintervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls