Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Download Full Version RCDDv14.1 BICSI Exam

Page: 6 / 12
Total 320 questions

BICSI Registered Communications Distribution Designer - RCDDv14.1 Questions and Answers

Question 21

After taking over a program, a program manager reviews the program's status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs The program manager establishes earned value (EV) metrics and determines that the program has a budget of USS2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000

Based on this information, the program manager determines which of the following?

Options:

A.

The schedule is US%30.000 under budget

B.

The cost is US$20.0O0 under budget

C.

The schedule is US$10.000 over budget

D.

The cost is USS20.000 over budget

Question 22

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved

What should the program manager do to ensure benefits realization?

Options:

A.

Conduct a program performance analysis based upon the deviation, and update the program business case to reflect the schedule delay

B.

Inform the program sponsor and the steering committee of the delay, and validate the program business case

C.

Analyze the impact of the delay, review risks, identify any corrective actions, and update the benefits management plan

D.

Update the program schedule, and escalate the issue to the program management office (PMO) to accelerate shipyard work.

Question 23

Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology Company B is excited about the joint marketing opportunity Company A's component Quality Assurance team has expressed concerns to you the program manager, Ural the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled

What is your MOST appropriate next step?

Options:

A.

Secure funding from another project that was cancelled

B.

Use an integrated change control process

C.

Use the available management reserve

D.

Advise Company B that funding and resources are not available

Question 24

A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?

Options:

A.

The component has released resources to meet program objectives

B.

The component has met the quality requirements to meet program objectives

C.

The component has met the schedule requirements to meet program objectives

D.

The component has met the benefits realization criteria to meet program objectives

Page: 6 / 12
Total 320 questions