Question 9

Which of the following is the best tool to use to identify the specific tasks needed to complete a project?

Options:

A.

PERT

B.

Activity network diagram

C.

Work breakdown structure

D.

Critical path method

Question 10

Which of the following performance measures in a balanced scorecard would have KPIs that are considered predictors for the metrics related to employee satisfaction, absentee rate, and employee turnover rate?

Options:

A.

Financial perspective

B.

Customer perspective

C.

Internal business processes perspective

D.

Learning and growth perspective

Question 11

Which of the following distributions contains more observations below the average than above the average?

Options:

A.

Gaussian

B.

Exponential

C.

Binomial

D.

Hypergeometric

Question 12

Which of the following actions is part of pre-experimental planning?

Options:

A.

Determining critical values

B.

Selecting the intended response variable

C.

Increasing the number of experiments and reducing the sample size in each

D.

Ensuring that only one person conducts each experiment