Question 21

What does the material type influence?

Note: There are 2 correct answers to this question.

Options:

A.

Which document types and class categories are allowed

B.

Which material master screens appear and in which sequence

C.

Whether the material is produced in-house, procured externally, or both

D.

Which plant-specific and plant-independent statuses are allowed

Question 22

What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?

Note: There are 2 correct answers to this question.

Options:

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities

C.

The Change Planning Direction indicator is set in the strategy profile

D.

Alternative work centers are fully occupied.

Question 23

in your Plant, MRP is activated.

which options do you have to exclude a material from the MRP run?

Note: there are 2 correct answers to this question.

Options:

A.

Use a specific material status

B.

Use a specific material group

C.

Use a specific MRP type

D.

Use a specific MRP list

Question 24

During production order creation, several valid production versions are found. How does the system choose the production version?

Options:

A.

Lot size or material cost

B.

Validity period or sales order

C.

Planned order or material number

D.

Alphanumeric or quota arrangement